Overview
Global Energy Monitor tracks 4 units or phases at this site (operating 2.82 GW).
Technology: combined cycle; fuel: natural gas, fossil liquids: diesel, natural gas.
Ownership: PT PLN Indonesia Power (parent company: PT PLN (Persero)).
Its 4 operating units were commissioned between 1994 and 2019.
Why it matters
- The largest oil- and gas-fired power station in Indonesia by capacity, out of 59 operating oil & gas facilities tracked in the country.
- Provides about 11% of Indonesia's operating oil & gas capacity and roughly 2.9% of all operating power capacity in the country in the dataset.
- Ranks #60 worldwide among oil & gas facilities of the same status group by capacity.
- At a typical capacity factor of 40% for this technology, it would generate roughly 9.9 TWh of electricity a year (indicative estimate).
Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.
Oil & gas power in Indonesia
Indonesia has 26.0 GW of operating oil & gas capacity across 59 plants in the Global Energy Monitor dataset — 27% of the country's total operating power capacity of 96.5 GW.
The oil & gas pipeline in Indonesia includes 960 MW under construction and 13.7 GW at earlier planning stages.
Other major oil & gas plants in Indonesia include Muara Tawar power station (2.79 GW), Gresik power station (2.18 GW) and Muara Karang power station (2.13 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| 1 | 590 MW | combined cycle | 1994 | ||
| 2 | 590 MW | combined cycle | 1994 | ||
| 3 | 750 MW | combined cycle | 2012 | ||
| 4 | 892 MW | combined cycle | 2019 |
How gas & oil power plants work
Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.
Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.
Technology at Tanjung Priok power station
Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Location
Tanjung Priok power station is located in Jawa, Indonesia, at approximately -6.1102, 106.8671. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Tanjung Priok power station is owned by PT PLN Indonesia Power. The ultimate parent company is PT PLN (Persero). Across the dataset, PT PLN (Persero) is linked to 174 power plants with 43.5 GW of operating capacity.
Frequently asked questions
What is the capacity of Tanjung Priok power station?
Tanjung Priok power station has a capacity of 2.82 GW according to the latest Global Energy Monitor data. This figure covers the 4 units or phases listed for the site.
What type of facility is Tanjung Priok power station?
Tanjung Priok power station is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Who owns Tanjung Priok power station?
Tanjung Priok power station is owned by PT PLN Indonesia Power. The ultimate parent company is PT PLN (Persero).
Where is Tanjung Priok power station located?
It is located in Jawa, Indonesia. Approximate coordinates: -6.1102, 106.8671.
Is Tanjung Priok power station operational?
According to the latest data, Tanjung Priok power station is in operation. Operating means the facility is built and in commercial service.
When did Tanjung Priok power station start operating?
Start year: 1994. Current status: Operating. Its 4 operating units were commissioned between 1994 and 2019.
How much electricity does Tanjung Priok power station generate?
Actual output data are not published for every plant. As an indicative estimate, Tanjung Priok power station would produce about 9.9 TWh a year, assuming a capacity factor of 40%, which is typical for this technology.
How big is Tanjung Priok power station compared with other facilities in Indonesia?
Tanjung Priok power station ranks #1 by capacity among 59 comparable oil & gas facilities tracked in Indonesia.