Global Energy Monitor tracks 12 units or phases at this site (operating 3.36 GW, under construction 760 MW, planned 380 MW).
Technology: unknown, supercritical; fuel: coal: unknown.
Ownership: PT Sulawesi Mining Investment (parent company: Dingxin Group; PT Bintang Delapan Group).
Its 9 operating units were commissioned between 2021 and 2024. 2 further units or phases are scheduled to come online in 2025.
Why it matters
- The 4th-largest coal-fired power station in Indonesia by capacity (of 98 operating coal facilities tracked).
- Provides about 5.5% of Indonesia's operating coal capacity and roughly 3.5% of all operating power capacity in the country in the dataset.
- Ranks #85 worldwide among coal facilities of the same status group by capacity.
- At a typical capacity factor of 50% for this technology, it would generate roughly 15 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in Indonesia
Indonesia has 60.6 GW of operating coal capacity across 98 plants in the Global Energy Monitor dataset — 63% of the country's total operating power capacity of 96.5 GW.
The coal pipeline in Indonesia includes 5.28 GW under construction and 10.4 GW at earlier planning stages.
Other major coal plants in Indonesia include Banten Suralaya power station (6.03 GW), Tanjung Jati B power station (4.64 GW) and Weda Bay power station (4.54 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Unit 1 | 350 MW | unknown | 2021 | ||
| Unit 2 | 350 MW | unknown | 2022 | ||
| Unit 3 | 380 MW | unknown | 2023 | ||
| Unit 4 | 380 MW | supercritical | 2023 | ||
| Unit 5 | 380 MW | supercritical | 2023 | ||
| Unit 6 | 380 MW | supercritical | 2023 | ||
| Unit 7 | 380 MW | supercritical | 2023 | ||
| Unit 8 | 380 MW | supercritical | 2024 | ||
| Unit 9 | 380 MW | supercritical | 2024 | ||
| Unit 10 | 380 MW | Construction | unknown | 2025 | |
| Unit 11 | 380 MW | Construction | unknown | 2025 | |
| Unit 12 | 380 MW | Pre-construction | unknown |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Sulawesi Labota power station
Supercritical units operate above the critical pressure of water, reaching efficiencies of roughly 38–42% and lower emissions per megawatt-hour than subcritical units.
Location
Sulawesi Labota power station is located in Sulawesi, Indonesia, at approximately -2.8679, 122.1771. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Sulawesi Labota power station is owned by PT Sulawesi Mining Investment. The ultimate parent company is Dingxin Group; PT Bintang Delapan Group.
Frequently asked questions
What is the capacity of Sulawesi Labota power station?
Sulawesi Labota power station has a capacity of 3.36 GW according to the latest Global Energy Monitor data. This figure covers the 12 units or phases listed for the site.
What type of facility is Sulawesi Labota power station?
Sulawesi Labota power station is a coal-fired power station. Supercritical units operate above the critical pressure of water, reaching efficiencies of roughly 38–42% and lower emissions per megawatt-hour than subcritical units.
Who owns Sulawesi Labota power station?
Sulawesi Labota power station is owned by PT Sulawesi Mining Investment. The ultimate parent company is Dingxin Group; PT Bintang Delapan Group.
Where is Sulawesi Labota power station located?
It is located in Sulawesi, Indonesia. Approximate coordinates: -2.8679, 122.1771.
Is Sulawesi Labota power station operational?
According to the latest data, Sulawesi Labota power station is in operation. Operating means the facility is built and in commercial service.
When did Sulawesi Labota power station start operating?
Start year: 2021. Current status: Operating. Its 9 operating units were commissioned between 2021 and 2024. 2 further units or phases are scheduled to come online in 2025.
How much electricity does Sulawesi Labota power station generate?
Actual output data are not published for every plant. As an indicative estimate, Sulawesi Labota power station would produce about 15 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Sulawesi Labota power station compared with other facilities in Indonesia?
Sulawesi Labota power station ranks #4 by capacity among 98 comparable coal facilities tracked in Indonesia.