Overview
Global Energy Monitor tracks 2 units or phases at this site (operating 1.98 GW).
Technology: ultra-supercritical; fuel: coal: unknown.
Ownership: PT Shenhua Guohua Pembangkitan Jawa Bali (parent company: China Shenhua Energy Co Ltd; PT PLN (Persero)).
Its 2 operating units were commissioned between 2019 and 2020.
Why it matters
- The 7th-largest coal-fired power station in Indonesia by capacity (of 98 operating coal facilities tracked).
- Provides about 3.3% of Indonesia's operating coal capacity and roughly 2.1% of all operating power capacity in the country in the dataset.
- At a typical capacity factor of 50% for this technology, it would generate roughly 8.7 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in Indonesia
Indonesia has 60.6 GW of operating coal capacity across 98 plants in the Global Energy Monitor dataset — 63% of the country's total operating power capacity of 96.5 GW.
The coal pipeline in Indonesia includes 5.28 GW under construction and 10.4 GW at earlier planning stages.
Other major coal plants in Indonesia include Banten Suralaya power station (6.03 GW), Tanjung Jati B power station (4.64 GW) and Weda Bay power station (4.54 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Unit 1 | 991 MW | ultra-supercritical | 2019 | ||
| Unit 2 | 991 MW | ultra-supercritical | 2020 |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Jawa-7 power station
Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.
Location
Jawa-7 power station is located in Jawa, Indonesia, at approximately -5.9917, 106.1008. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Jawa-7 power station is owned by PT Shenhua Guohua Pembangkitan Jawa Bali. The ultimate parent company is China Shenhua Energy Co Ltd; PT PLN (Persero). Across the dataset, China Shenhua Energy Co Ltd is linked to 83 power plants in 2 countries, with 138.6 GW of operating capacity.
Frequently asked questions
What is the capacity of Jawa-7 power station?
Jawa-7 power station has a capacity of 1.98 GW according to the latest Global Energy Monitor data. This figure covers the 2 units or phases listed for the site.
What type of facility is Jawa-7 power station?
Jawa-7 power station is a coal-fired power station. Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.
Who owns Jawa-7 power station?
Jawa-7 power station is owned by PT Shenhua Guohua Pembangkitan Jawa Bali. The ultimate parent company is China Shenhua Energy Co Ltd; PT PLN (Persero).
Where is Jawa-7 power station located?
It is located in Jawa, Indonesia. Approximate coordinates: -5.9917, 106.1008.
Is Jawa-7 power station operational?
According to the latest data, Jawa-7 power station is in operation. Operating means the facility is built and in commercial service.
When did Jawa-7 power station start operating?
Start year: 2019. Current status: Operating. Its 2 operating units were commissioned between 2019 and 2020.
How much electricity does Jawa-7 power station generate?
Actual output data are not published for every plant. As an indicative estimate, Jawa-7 power station would produce about 8.7 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Jawa-7 power station compared with other facilities in Indonesia?
Jawa-7 power station ranks #7 by capacity among 98 comparable coal facilities tracked in Indonesia.