Overview
Global Energy Monitor tracks 5 units or phases at this site (under construction 1.05 GW, planned 1.20 GW).
Technology: supercritical; fuel: coal: unknown.
Ownership: Gallant Venture Ltd.
Why it matters
- The 7th-largest coal-fired power station in Indonesia by capacity (of 126 operating, under-construction and planned coal facilities tracked).
- If completed, it would add 2.25 GW to Indonesia's coal fleet — equivalent to 3.7% of today's operating coal capacity.
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in Indonesia
Indonesia has 60.6 GW of operating coal capacity across 98 plants in the Global Energy Monitor dataset — 63% of the country's total operating power capacity of 96.5 GW.
The coal pipeline in Indonesia includes 5.28 GW under construction and 10.4 GW at earlier planning stages.
Other major coal plants in Indonesia include Banten Suralaya power station (6.03 GW), Tanjung Jati B power station (4.64 GW) and Weda Bay power station (4.54 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Phase I Unit 1 | 350 MW | Construction | supercritical | ||
| Phase I Unit 2 | 350 MW | Construction | supercritical | ||
| Phase I Unit 3 | 350 MW | Construction | supercritical | ||
| Phase II Unit 1 | 600 MW | Pre-construction | supercritical | ||
| Phase II Unit 2 | 600 MW | Pre-construction | supercritical |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Gallant Venture power station
Supercritical units operate above the critical pressure of water, reaching efficiencies of roughly 38–42% and lower emissions per megawatt-hour than subcritical units.
Location
Gallant Venture power station is located in Sumatera, Indonesia, at approximately 0.9576, 104.0486. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Gallant Venture power station is owned by Gallant Venture Ltd. Across the dataset, Gallant Venture Ltd is linked to 3 power plants with 114 MW of operating capacity.
Frequently asked questions
What is the capacity of Gallant Venture power station?
Gallant Venture power station has a capacity of 2.25 GW according to the latest Global Energy Monitor data. This figure covers the 5 units or phases listed for the site.
What type of facility is Gallant Venture power station?
Gallant Venture power station is a coal-fired power station. Supercritical units operate above the critical pressure of water, reaching efficiencies of roughly 38–42% and lower emissions per megawatt-hour than subcritical units.
Who owns Gallant Venture power station?
Gallant Venture power station is owned by Gallant Venture Ltd.
Where is Gallant Venture power station located?
It is located in Sumatera, Indonesia. Approximate coordinates: 0.9576, 104.0486.
Is Gallant Venture power station operational?
According to the latest data, Gallant Venture power station is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.
How big is Gallant Venture power station compared with other facilities in Indonesia?
Gallant Venture power station ranks #7 by capacity among 126 comparable coal facilities tracked in Indonesia.