bp and Iberdrola Start Up Spain’s Largest Green Hydrogen Plant at Castellón

bp and Iberdrola Start Up Spain’s Largest Green Hydrogen Plant at Castellón
Summary not found.

bp and Iberdrola have started operations at a 25-megawatt green hydrogen plant next to bp’s refinery in Castellón, eastern Spain, the companies said Thursday, bringing into service what they describe as Spain’s largest operating green hydrogen facility. The plant is owned equally by the two companies through their joint venture, Castellón Green Hydrogen S.L., and was confirmed as operational in parallel statements from bp and Iberdrola España, with the news picked up by Hydrogen Insight, Upstream Online, gasworld and other energy trade press.

From Grey to Green at the Refinery Gate

The electrolyser is designed to produce roughly 2,800 tonnes of green hydrogen a year, using renewable electricity to split water rather than reforming natural gas. That output is intended to displace part of the grey hydrogen bp’s Castellón refinery currently uses in its processing operations, output the companies say is responsible for a share of the refinery’s carbon footprint. bp and Iberdrola have said the switch is expected to avoid roughly 23,000 tonnes of carbon dioxide emissions annually once the plant is running at its intended capacity.

A Two-Year Build From Decision to Startup

bp and Iberdrola announced a final investment decision on the project in September 2024, describing it at the time as the first hydrogen project the two companies had undertaken together. Construction began in early 2025, and by March 2026 the companies said the build had reached roughly 90% completion. Construction work finished around mid-2026 and the facility moved into commissioning and testing before this week’s confirmation that commercial operations have begun. The companies have put the investment in the plant at more than €70 million.

Part of a Larger Valencia Hydrogen Push

The Castellón electrolyser is the first unit to come online from a broader hydrogen cluster bp first outlined for the Valencia region in 2023, under which the company has discussed investing in up to 2 gigawatts of electrolysis capacity at the site by 2030. bp and Iberdrola have also said they are examining options to expand green hydrogen output at Castellón beyond the initial 25 MW, with European Hy2USE programme funding under discussion to support that next phase, though the companies have not set a timeline or confirmed capacity for any expansion.

Why a 25 MW Plant Matters

By global electrolyser standards, 25 MW is a modest installation, but it marks one of a small number of green hydrogen plants in Europe that have reached commercial operation at an existing refinery rather than remaining at the planning or construction stage — a distinction that matters given how many larger hydrogen projects elsewhere, such as TotalEnergies’ $16 billion Magallanes project in Chile, have been delayed, scaled back or cancelled over the past two years on cost and demand concerns. For bp, the project offers a concrete, operating reference point for its refinery decarbonisation plans in Spain; for Iberdrola, it extends the utility’s green hydrogen portfolio beyond its earlier Puertollano plant into a second Spanish region.

Sources

  • bp, “bp and Iberdrola start operation of green hydrogen plant at Castellón refinery,” November 27, 2026 — plant capacity, output, emissions-reduction estimate, ownership structure.
  • Iberdrola España, statement confirming the start of operations at the Castellón green hydrogen plant, November 27, 2026 — investment figure, project history.
  • Hydrogen Insight and Upstream Online, “BP and Iberdrola start up Spain’s largest green hydrogen project,” November 27, 2026 — independent confirmation and context on the project timeline.