Poland’s Nuclear Developer Opens Second Track for AP1000 Equipment Orders
Poland’s state nuclear developer and its US contractors have moved to open a second channel for ordering long-lead reactor equipment at the country’s first nuclear power plant, aiming to shrink the schedule risk on a project that is still finalizing its main construction contract.
Polskie Elektrownie Jądrowe (PEJ), Bechtel and Westinghouse signed a letter of intent at the P-TEC industry forum in Warsaw on November 20, setting up a mechanism to start procuring a further batch of long-lead items (LLIs) for the plant’s first AP1000 unit before the engineering, procurement and construction (EPC) contract is finalized, according to World Nuclear News. The US partners also agreed to help PEJ negotiate financing support from export credit agencies for the new equipment orders.
A second wave of components
The move builds on a first round of ordering that PEJ authorized in October. Westinghouse has since placed conditional purchase orders with four Polish fabricators for structural modules of the reactor’s nuclear island: Mostostal Kielce (wall modules under scope CA02), Energomontaż-Północ Gdynia (module scope CA03), Mostostal Kraków (wall modules under scope CA05) and FAMAK (floor modules under scope CA20). In early November, Westinghouse also ordered Japan’s IHI Corporation to handle engineering and procurement for a containment vessel and an associated large steel module for the first unit.
Those orders fall under an existing Engineering Development Agreement (EDA) between PEJ and the Westinghouse-Bechtel consortium, which lets procurement proceed in parallel with EPC talks rather than waiting for a signed contract. The new letter of intent extends that same logic to a further set of components, though World Nuclear News reported that the specific equipment covered by this next batch has not been disclosed.
EPC contract still being negotiated
The plant, to be built at Lubiatowo-Kopalino in the Choczewo municipality on Poland’s Baltic coast, will house three Westinghouse AP1000 reactors. Poland selected the AP1000 technology in 2022, and PEJ signed an 18-month engineering services contract in 2023. Terms for the EDA were agreed in April 2025 and amended in December that year to extend design work on the nuclear island, turbine island and balance-of-plant systems, along with geological surveys at the site.
The parties reached agreement on the main commercial and legal terms of the EPC contract in September 2026 and are targeting a final, signed contract by the end of this year. Until that happens, the conditional purchase orders already placed with suppliers remain subject to the EPC negotiations being completed. EDF’s Arabelle Solutions was separately selected by Bechtel and Westinghouse to supply the half-speed steam turbine and generator sets for all three units, following a competitive technical and financial evaluation.
Why Warsaw is front-loading procurement
Long-lead items such as containment vessels and major structural modules routinely take years to engineer and fabricate, so ordering them before a final contract is signed is a common industry practice for first-of-a-kind nuclear projects, intended to prevent supplier lead times from becoming the critical path once construction formally begins. Reports on the project’s timeline have varied: one account points to construction starting in 2028, while another cites 2036 for commissioning of the first unit. The project’s cost has been estimated at around $20 billion in earlier reporting, though neither PEJ nor Westinghouse has published a final figure tied to the EPC contract still under negotiation.
Separately, Bechtel, Gdańsk University of Technology and the University of South Carolina signed a memorandum of cooperation at the same P-TEC forum covering nuclear education and workforce development, underscoring the scale of the skilled labor build-out the project will require in Pomerania.
Part of a broader nuclear buildout
Lubiatowo-Kopalino is Poland’s first nuclear power plant project, part of a broader push by Warsaw to cut reliance on coal-fired generation and diversify its power mix. PEJ has also applied in recent weeks for an early-works permit at the site, as the project moves step by step from design toward the start of physical construction, even as the formal EPC contract that will govern the bulk of the build remains unsigned. Poland is separately advancing a second nuclear plant, with PEJ, PGE and the energy ministry signing an agreement on that follow-on project.
Sources
- World Nuclear News, “Partners prepare to procure next batch of equipment for Polish plant,” November 20, 2026 — letter of intent, procurement mechanism, supplier orders, EPC and EDA timeline.
- World Nuclear News, “Poland begins ordering long-lead components for first AP1000,” October 2026 — initial PEJ authorization and supplier scopes.
- World Nuclear News, “Arabelle turbines selected for Polish plant” — turbine island supplier selection.
- Westinghouse Electric Company newsroom — AP1000 technology and site contract background.
Illustrative image. Photo: Rosatom Digital Press Office/АО «Аккую Нуклеар», CC BY 4.0, via Wikimedia Commons — source