Global Energy Monitor tracks 8 units or phases at this site (operating 1.78 GW, under construction 700 MW, shelved / mothballed 100 MW).
Technology: pressurized heavy water reactor.
Ownership: Nuclear Power Corporation Of India Ltd.
Its 6 operating units were commissioned between 1981 and 2025. 1 further units or phases are scheduled to come online in 2026.
Why it matters
- The 3rd-largest nuclear power plant in India by capacity (of 7 operating nuclear facilities tracked).
- Provides about 21% of India's operating nuclear capacity.
- At a typical capacity factor of 85% for this technology, it would generate roughly 13 TWh of electricity a year (indicative estimate).
Nuclear plants supply large volumes of low-carbon baseload electricity with very high capacity factors, so a single station can cover a significant share of national demand.
Nuclear power in India
India has 8.40 GW of operating nuclear capacity across 7 plants in the Global Energy Monitor dataset — 1.7% of the country's total operating power capacity of 485.3 GW.
The nuclear pipeline in India includes 1.70 GW under construction and 28.3 GW at earlier planning stages.
Other major nuclear plants in India include Kudankulam nuclear power plant (2.00 GW), Kakrapar nuclear power plant (1.84 GW) and Kalpakkam nuclear power plant (1.70 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| 1 | 100 MW | Mothballed | pressurized heavy water reactor | 1973 | |
| 2 | 200 MW | pressurized heavy water reactor | 1981 | ||
| 3 | 220 MW | pressurized heavy water reactor | 2000 | ||
| 4 | 220 MW | pressurized heavy water reactor | 2000 | ||
| 5 | 220 MW | pressurized heavy water reactor | 2010 | ||
| 6 | 220 MW | pressurized heavy water reactor | 2010 | ||
| 7 | 700 MW | pressurized heavy water reactor | 2025 | ||
| 8 | 700 MW | Construction | pressurized heavy water reactor | 2026 |
How nuclear power plants work
A nuclear power plant uses heat from controlled fission of uranium (or plutonium) fuel in a reactor core to produce steam, which drives a turbine-generator in the same way as a thermal power station. The reactor is surrounded by multiple safety barriers and a containment building.
Nuclear units typically run more than 90% of the hours in a year, so a single large reactor can supply several terawatt-hours of almost carbon-free electricity annually. Construction times are long and capital costs high, but fuel costs are low and plants are often licensed to operate for 60 years or more.
Technology at Rajasthan nuclear power plant
Pressurised heavy water reactors (PHWR), such as the CANDU design, use heavy water as moderator and coolant and can run on natural uranium.
Location
Rajasthan nuclear power plant is located in Rajasthan, India, at approximately 24.8747, 75.6189. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Rajasthan nuclear power plant is owned by Nuclear Power Corporation Of India Ltd. Across the dataset, Nuclear Power Corporation Of India Ltd is linked to 14 power plants with 8.40 GW of operating capacity.
Frequently asked questions
What is the capacity of Rajasthan nuclear power plant?
Rajasthan nuclear power plant has a capacity of 1.78 GW according to the latest Global Energy Monitor data. This figure covers the 8 units or phases listed for the site.
What type of facility is Rajasthan nuclear power plant?
Rajasthan nuclear power plant is a nuclear power plant. Pressurised heavy water reactors (PHWR), such as the CANDU design, use heavy water as moderator and coolant and can run on natural uranium.
Who owns Rajasthan nuclear power plant?
Rajasthan nuclear power plant is owned by Nuclear Power Corporation Of India Ltd.
Where is Rajasthan nuclear power plant located?
It is located in Rajasthan, India. Approximate coordinates: 24.8747, 75.6189.
Is Rajasthan nuclear power plant operational?
According to the latest data, Rajasthan nuclear power plant is in operation. Operating means the facility is built and in commercial service.
When did Rajasthan nuclear power plant start operating?
Start year: 1981. Current status: Operating. Its 6 operating units were commissioned between 1981 and 2025. 1 further units or phases are scheduled to come online in 2026.
How much electricity does Rajasthan nuclear power plant generate?
Actual output data are not published for every plant. As an indicative estimate, Rajasthan nuclear power plant would produce about 13 TWh a year, assuming a capacity factor of 85%, which is typical for this technology.
How big is Rajasthan nuclear power plant compared with other facilities in India?
Rajasthan nuclear power plant ranks #3 by capacity among 7 comparable nuclear facilities tracked in India.