Overview
Global Energy Monitor tracks 8 units or phases at this site (operating 2.32 GW, planned 1.32 GW).
Technology: subcritical, supercritical, ultra-supercritical; fuel: coal: subbituminous.
Ownership: Rajasthan Rajya Vidyut Utpadan Nigam Ltd; NTPC Ltd.
Its 6 operating units were commissioned between 2009 and 2018. 2 further units or phases are scheduled to come online in 2029.
Why it matters
- The 23rd-largest coal-fired power station in India by capacity (of 285 operating coal facilities tracked).
- At a typical capacity factor of 50% for this technology, it would generate roughly 10 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in India
India has 253.8 GW of operating coal capacity across 285 plants in the Global Energy Monitor dataset — 52% of the country's total operating power capacity of 485.3 GW.
The coal pipeline in India includes 20.4 GW under construction and 35.6 GW at earlier planning stages.
Other major coal plants in India include Vindhyachal power station (4.76 GW), Mundra Thermal Power Project (Adani) (4.62 GW) and Ramagundam power station (4.20 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Unit 1 | 250 MW | subcritical | 2009 | ||
| Unit 2 | 250 MW | subcritical | 2010 | ||
| Unit 3 | 250 MW | subcritical | 2013 | ||
| Unit 4 | 250 MW | subcritical | 2014 | ||
| Unit 5 | 660 MW | supercritical | 2017 | ||
| Unit 6 | 660 MW | supercritical | 2018 | ||
| Unit 7 | 660 MW | Pre-construction | ultra-supercritical | 2029 | |
| Unit 8 | 660 MW | Pre-construction | ultra-supercritical | 2029 |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Chhabra Thermal Power Station
Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Location
Chhabra Thermal Power Station is located in Rajasthan, India, at approximately 24.6343, 77.0385. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Chhabra Thermal Power Station is owned by Rajasthan Rajya Vidyut Utpadan Nigam Ltd; NTPC Ltd. Across the dataset, Rajasthan Rajya Vidyut Utpadan Nigam Ltd is linked to 14 power plants with 8.24 GW of operating capacity.
Frequently asked questions
What is the capacity of Chhabra Thermal Power Station?
Chhabra Thermal Power Station has a capacity of 2.32 GW according to the latest Global Energy Monitor data. This figure covers the 8 units or phases listed for the site.
What type of facility is Chhabra Thermal Power Station?
Chhabra Thermal Power Station is a coal-fired power station. Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.
Who owns Chhabra Thermal Power Station?
Chhabra Thermal Power Station is owned by Rajasthan Rajya Vidyut Utpadan Nigam Ltd; NTPC Ltd.
Where is Chhabra Thermal Power Station located?
It is located in Rajasthan, India. Approximate coordinates: 24.6343, 77.0385.
Is Chhabra Thermal Power Station operational?
According to the latest data, Chhabra Thermal Power Station is in operation. Operating means the facility is built and in commercial service.
When did Chhabra Thermal Power Station start operating?
Start year: 2009. Current status: Operating. Its 6 operating units were commissioned between 2009 and 2018. 2 further units or phases are scheduled to come online in 2029.
How much electricity does Chhabra Thermal Power Station generate?
Actual output data are not published for every plant. As an indicative estimate, Chhabra Thermal Power Station would produce about 10 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Chhabra Thermal Power Station compared with other facilities in India?
Chhabra Thermal Power Station ranks #23 by capacity among 285 comparable coal facilities tracked in India.