Evecon and Mirova are putting the finishing touches on a 55 MW/250 MWh battery at the Kirikmäe solar park in western Estonia, a project the two companies say will be the largest battery energy storage system by capacity in the Baltic states once it clears final grid and market testing. The battery is being added to the existing 77.5 MW Kirikmäe solar farm near the town of Lihula, turning the site into what its developers call the most powerful solar-plus-storage hybrid park in the region. WiSo Engineering, the Tallinn-based contractor that built the original solar plant, says the storage unit is technically complete, with grid and market tests still being finalized before commercial operation begins.

A Solar Park Rebuilt Into a Hybrid Asset

Kirikmäe’s 77.5 MW of solar capacity has been running since October 2024. The battery retrofit is a separate, later phase: construction on the 250 MWh storage unit began in January 2026, according to WiSo Engineering. The project is owned by the Baltic Renewable Energy Platform (BREP), a joint venture between Estonian energy company Evecon and French infrastructure investor Mirova. Evecon and Mirova say they have put €110 million ($120.7 million) into completing the hybridization. BREP separately lined up an €85 million long-term financing package from Swedish bank Swedbank, used both to refinance its existing solar portfolio and to help fund construction of the Kirikmäe battery.

A Flexibility Deal With a German Buyer

BREP has already locked in a buyer for the power the hybrid plant will help manage. The platform signed a 10-year flexibility and power purchase agreement (FPPA) with German energy trading company Pure Energy, first announced in February 2026. The deal covers not just Kirikmäe but two other BREP solar plants, the 15.5 MW Imavere and 12.8 MW Lohu Mets sites, and is described by the companies as the first agreement of its kind signed in the Baltic states. Pairing a battery with an existing solar asset lets BREP shift some of that generation to hours when prices or grid needs are different, rather than selling everything at the moment the sun is shining.

Why the Baltics Are Racing to Add Batteries

Evecon CEO Karl-Joonatan Kvell called the Kirikmäe battery “an important step towards increased Estonian energy security,” framing it as part of a shift toward an electricity system that leans more on power generated locally. That framing matters in the Baltic context: Estonia, Latvia and Lithuania disconnected from Russia’s grid and synchronized with the continental European system in February 2025, and have since had to manage their own grid frequency and balancing needs rather than relying on Russian infrastructure. That shift has made fast-reacting domestic capacity, including batteries, more valuable to the three countries’ grid operators.

Kirikmäe is not an isolated case. Evecon, Mirova and French developer Corsica Sole switched on a separate 100 MW/200 MWh battery, Hertz 1, in Kiisa in February 2026, with a twin unit, Hertz 2, following in July 2026. A third large project, a 192 MW/420 MWh battery backed by Taaleri Energia and KJK Capital, started construction in September 2026 and is expected to be operating by November 2027. It follows a pattern seen elsewhere in utility-scale storage this year, from Masdar’s $950 million Lockhart solar-storage hub in California to X-ELIO’s 590 MW of US and Australian battery orders, where developers are increasingly pairing or retrofitting storage onto existing solar fleets rather than building standalone plants. Combined, the Estonian projects point to a fast-building pipeline of grid-scale storage as the Baltic states adjust to standalone grid operation, part of a wider financing wave behind battery projects this year.

Who Is Behind the Project

Mirova is the responsible-investing arm of French asset manager Natixis Investment Managers, and has backed renewable infrastructure across Europe through vehicles such as BREP rather than taking majority ownership of single national utilities. Evecon is a smaller, Estonia-based developer that has built its portfolio mainly around solar and storage assets inside the country, making the Mirova tie-up a way to bring in outside capital for projects at a scale a domestic developer alone would struggle to finance. The repeated pairing of Evecon, Mirova and, on some projects, Corsica Sole across Kirikmäe, Hertz 1 and Hertz 2 suggests a standing partnership structure rather than one-off joint ventures, with WiSo Engineering acting as the recurring construction partner on the Evecon-Mirova side.

Sources

Illustrative image. Photo: Kecko from Eastern Switzerland, CC BY 2.0, via Wikimedia Commons — source

Leave a Comment

Your email address will not be published. Required fields are marked *

Related Posts