Overview
Technology: pumped storage.
Ownership: PT PLN (Persero).
Why it matters
- The 6th-largest hydropower plant in Indonesia by capacity (of 68 operating, under-construction and planned hydropower facilities tracked).
- If completed, it would add 1.04 GW to Indonesia's hydropower fleet — equivalent to 19% of today's operating hydropower capacity.
Hydropower provides renewable electricity and, where reservoirs exist, dispatchable output and storage that help stabilise the grid; output varies with rainfall and river flows.
Hydropower power in Indonesia
Indonesia has 5.58 GW of operating hydropower capacity across 35 plants in the Global Energy Monitor dataset — 5.8% of the country's total operating power capacity of 96.5 GW.
The hydropower pipeline in Indonesia includes 3.43 GW under construction and 14.5 GW at earlier planning stages.
Other major hydropower plants in Indonesia include Mentarang hydroelectric plant (1.38 GW) and Cirata hydroelectric plant (1.01 GW).
How hydropower plants work
Hydropower plants convert the energy of falling or flowing water into electricity: water passes through turbines placed at the foot of a dam or along a diversion channel, and the turbines drive generators. Output depends on the height of the water drop (the head) and the volume of water flowing.
Reservoir and pumped-storage schemes can store energy and release it within minutes, which makes hydropower one of the most flexible sources on the grid. Annual generation varies with rainfall and snowmelt, and large dams can have significant effects on river ecosystems and downstream water use.
Technology at Upper Cisokan hydroelectric plant
As a pumped-storage scheme it pumps water to an upper reservoir when power is cheap and releases it through turbines at peak times, acting as a large grid-scale battery.
Location
Upper Cisokan hydroelectric plant is located in West Java Province, Indonesia, at approximately -6.9458, 107.2173. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Upper Cisokan hydroelectric plant is owned by PT PLN (Persero). Across the dataset, PT PLN (Persero) is linked to 174 power plants with 43.5 GW of operating capacity.
Frequently asked questions
What is the capacity of Upper Cisokan hydroelectric plant?
Upper Cisokan hydroelectric plant has a capacity of 1.04 GW according to the latest Global Energy Monitor data.
What type of facility is Upper Cisokan hydroelectric plant?
Upper Cisokan hydroelectric plant is a hydropower plant. As a pumped-storage scheme it pumps water to an upper reservoir when power is cheap and releases it through turbines at peak times, acting as a large grid-scale battery.
Who owns Upper Cisokan hydroelectric plant?
Upper Cisokan hydroelectric plant is owned by PT PLN (Persero).
Where is Upper Cisokan hydroelectric plant located?
It is located in West Java Province, Indonesia. Approximate coordinates: -6.9458, 107.2173.
Is Upper Cisokan hydroelectric plant operational?
According to the latest data, Upper Cisokan hydroelectric plant is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.
When is Upper Cisokan hydroelectric plant expected to start?
Start year: 2027. Current status: Construction.
How big is Upper Cisokan hydroelectric plant compared with other facilities in Indonesia?
Upper Cisokan hydroelectric plant ranks #6 by capacity among 68 comparable hydropower facilities tracked in Indonesia.