LNG import terminal · Japan

Higashi Ohgishima LNG Terminal

Higashi Ohgishima LNG Terminal is a 13.2 mtpa LNG import (regasification) terminal in Kanagawa, Japan. It is currently in operation, with operations starting in 1984.

13.2 mtpaCapacity
OperatingStatus
1984Start year
View on the interactive map →

Overview

The tracker lists 2 trains, units or expansion phases at the terminal.

Capacity is expressed in million tonnes per annum (mtpa) of LNG that can be received and regasified.

One mtpa of LNG corresponds to roughly 1.36 billion cubic metres of natural gas per year, so this capacity equals about 18.0 bcm/y of gas.

Ownership: JERA Co Inc (parent company: Chubu Electric Power Co Inc; Tokyo Electric Power Co).

Why it matters

  • The 3rd-largest LNG import (regasification) terminal in Japan by capacity (of 45 operating lng import terminal facilities tracked).
  • Ranks #15 worldwide among lng import terminal facilities of the same status group by capacity.

Import terminals regasify liquefied natural gas delivered by tanker and inject it into the grid, giving countries access to seaborne gas supply from many exporters.

LNG terminals in Japan

The dataset tracks 45 lng terminals in Japan, including operating, planned and shelved projects.

Japan has 242.2 mtpa of operating LNG import capacity across 45 terminals.

See the full list: LNG terminals in Japan →

Trains and phases

Unit / phaseCapacityStatusTechnologyStartRetired
— 13.2 mtpa Operating 1984
Expansion 6.00 mtpa Cancelled

How lng terminals work

An LNG import terminal receives liquefied natural gas from tankers, stores it at around −162 °C in insulated tanks and warms it back into gas (regasification) before sending it into the pipeline grid. Many newer terminals are floating storage and regasification units (FSRUs), which can be installed much faster than onshore plants.

Import terminals give countries access to gas from many exporters worldwide, improving supply security and price competition — a role that became especially visible in Europe after 2022.

Location

Location is approximate. Imagery © Esri, Maxar, Earthstar Geographics

Higashi Ohgishima LNG Terminal is located in Kanagawa, Japan, at approximately 35.4954, 139.7450. Open the interactive map to explore nearby power plants, high-voltage lines and substations.

Ownership

Higashi Ohgishima LNG Terminal is owned by JERA Co Inc. The ultimate parent company is Chubu Electric Power Co Inc; Tokyo Electric Power Co. Across the dataset, Chubu Electric Power Co Inc is linked to 15 lng terminals.

Frequently asked questions

What is the capacity of Higashi Ohgishima LNG Terminal?

Higashi Ohgishima LNG Terminal has a capacity of 13.2 mtpa according to the latest Global Energy Monitor data. This figure covers the 2 units or phases listed for the site.

What type of facility is Higashi Ohgishima LNG Terminal?

Higashi Ohgishima LNG Terminal is a LNG import (regasification) terminal.

Who owns Higashi Ohgishima LNG Terminal?

Higashi Ohgishima LNG Terminal is owned by JERA Co Inc. The ultimate parent company is Chubu Electric Power Co Inc; Tokyo Electric Power Co.

Where is Higashi Ohgishima LNG Terminal located?

It is located in Kanagawa, Japan. Approximate coordinates: 35.4954, 139.7450.

Is Higashi Ohgishima LNG Terminal operational?

According to the latest data, Higashi Ohgishima LNG Terminal is in operation. Operating means the facility is built and in commercial service.

When did Higashi Ohgishima LNG Terminal start operating?

Start year: 1984. Current status: Operating.

How big is Higashi Ohgishima LNG Terminal compared with other facilities in Japan?

Higashi Ohgishima LNG Terminal ranks #3 by capacity among 45 comparable lng import terminal facilities tracked in Japan.

Nearby energy infrastructure

Other assets of the same owner

Sources and methodology

Source: Global Energy Monitor, Global Gas Infrastructure Tracker, 2025-11 release. Full project profile on GEM.wiki. Last updated: 9 October 2026.

Capacity, status, ownership and unit details come from Global Energy Monitor's public trackers, which are compiled from company reports, government filings and news coverage and updated several times a year. Rankings and shares are calculated by The Daily Energy from the same dataset. Estimated annual generation uses typical capacity factors for each technology and is indicative only.

Data: Global Energy Monitor (GIPT 2026-09, GGIT 2025-11, GOIT 2026-06, GOGET 2026-03, GCMT 2026-08, OSM 2026-10) licensed under CC BY 4.0; transmission grid © OpenStreetMap contributors (ODbL). Compiled and published by The Daily Energy.