Overview
Global Energy Monitor tracks 10 units or phases at this site (operating 3.52 GW).
Technology: combined cycle; fuel: natural gas.
Ownership: Saudi Electricity Co.
Its 10 operating units were commissioned between 2015 and 2018.
Why it matters
- The 8th-largest oil- and gas-fired power station in Saudi Arabia by capacity (of 97 operating oil & gas facilities tracked).
- Provides about 3.5% of Saudi Arabia's operating oil & gas capacity and roughly 3.1% of all operating power capacity in the country in the dataset.
- Ranks #32 worldwide among oil & gas facilities of the same status group by capacity.
- At a typical capacity factor of 40% for this technology, it would generate roughly 12 TWh of electricity a year (indicative estimate).
Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.
Oil & gas power in Saudi Arabia
Saudi Arabia has 100.6 GW of operating oil & gas capacity across 97 plants in the Global Energy Monitor dataset — 89% of the country's total operating power capacity of 112.6 GW.
The oil & gas pipeline in Saudi Arabia includes 14.9 GW under construction and 6.00 GW at earlier planning stages.
Other major oil & gas plants in Saudi Arabia include Rabigh 1 power plant (4.48 GW), Ghazlan power plant (4.26 GW) and Qurayyah CC power plant (4.10 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| CC1 | 352 MW | combined cycle | 2015 | ||
| CC2 | 352 MW | combined cycle | 2015 | ||
| CC3 | 352 MW | combined cycle | 2015 | ||
| CC4 | 352 MW | combined cycle | 2016 | ||
| CC5 | 352 MW | combined cycle | 2018 | ||
| CC6 | 352 MW | combined cycle | 2016 | ||
| CC7 | 352 MW | combined cycle | 2016 | ||
| CC8 | 352 MW | combined cycle | 2016 | ||
| CC9 | 352 MW | combined cycle | 2016 | ||
| CC10 | 352 MW | combined cycle | 2016 |
How gas & oil power plants work
Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.
Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.
Technology at Riyadh 10 power plant
Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Location
Riyadh 10 power plant is located in Riyadh, Saudi Arabia, at approximately 24.4206, 47.0195. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Riyadh 10 power plant is owned by Saudi Electricity Co. Across the dataset, Saudi Electricity Co is linked to 56 power plants with 69.7 GW of operating capacity.
Frequently asked questions
What is the capacity of Riyadh 10 power plant?
Riyadh 10 power plant has a capacity of 3.52 GW according to the latest Global Energy Monitor data. This figure covers the 10 units or phases listed for the site.
What type of facility is Riyadh 10 power plant?
Riyadh 10 power plant is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Who owns Riyadh 10 power plant?
Riyadh 10 power plant is owned by Saudi Electricity Co.
Where is Riyadh 10 power plant located?
It is located in Riyadh, Saudi Arabia. Approximate coordinates: 24.4206, 47.0195.
Is Riyadh 10 power plant operational?
According to the latest data, Riyadh 10 power plant is in operation. Operating means the facility is built and in commercial service.
When did Riyadh 10 power plant start operating?
Start year: 2015. Current status: Operating. Its 10 operating units were commissioned between 2015 and 2018.
How much electricity does Riyadh 10 power plant generate?
Actual output data are not published for every plant. As an indicative estimate, Riyadh 10 power plant would produce about 12 TWh a year, assuming a capacity factor of 40%, which is typical for this technology.
How big is Riyadh 10 power plant compared with other facilities in Saudi Arabia?
Riyadh 10 power plant ranks #8 by capacity among 97 comparable oil & gas facilities tracked in Saudi Arabia.