Navoi power station is a 2.15 GW oil- and gas-fired power station located in Navoiy, Uzbekistan. The facility is currently in operation, with its first unit entering service in 1964.

2.15 GWCapacity
OperatingStatus
1964Start year
View on the interactive map →

Overview

Global Energy Monitor tracks 13 units or phases at this site (operating 2.15 GW, under construction 650 MW, planned 650 MW).

Technology: combined cycle, steam turbine; fuel: natural gas.

Ownership: Navoi Thermal Power Plant JSC (parent company: Thermal Power Stations JSC).

Its 11 operating units were commissioned between 1964 and 2020. 1 further units or phases are scheduled to come online in 2026.

Why it matters

  • The 3rd-largest oil- and gas-fired power station in Uzbekistan by capacity (of 17 operating oil & gas facilities tracked).
  • Provides about 14% of Uzbekistan's operating oil & gas capacity and roughly 9% of all operating power capacity in the country in the dataset.
  • At a typical capacity factor of 40% for this technology, it would generate roughly 7.5 TWh of electricity a year (indicative estimate).

Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.

Oil & gas power in Uzbekistan

Uzbekistan has 15.6 GW of operating oil & gas capacity across 17 plants in the Global Energy Monitor dataset — 65% of the country's total operating power capacity of 24.0 GW.

The oil & gas pipeline in Uzbekistan includes 3.68 GW under construction and 200 MW at earlier planning stages.

Other major oil & gas plants in Uzbekistan include Sirdaryo power station (3.20 GW), Talimarjan power station (2.77 GW) and Tashkent power station (1.78 GW).

See the full list: Gas & oil power plants in Uzbekistan →

Units and phases

Unit / phaseCapacityStatusTechnologyStartRetired
CC1 478 MW Operating combined cycle 2012
CC2 473 MW Operating combined cycle 2020
CC3 650 MW Construction combined cycle 2026
CC4 650 MW Announced combined cycle
ST3 150 MW Operating steam turbine 1964
ST4 150 MW Operating steam turbine 1965
ST5 50 MW Operating steam turbine 1966
ST6 60 MW Operating steam turbine 1967
ST7 50 MW Operating steam turbine 1971
ST8 160 MW Operating steam turbine 1968
ST9 160 MW Operating steam turbine 1969
ST11 210 MW Operating steam turbine 1980
ST12 210 MW Operating steam turbine 1981

How gas & oil power plants work

Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.

Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.

Technology at Navoi power station

Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant. Steam-turbine units burn fuel in a boiler to raise steam; they are generally older and less flexible than combined-cycle plants.

Location

Imagery © Esri, Maxar, Earthstar Geographics

Navoi power station is located in Navoiy, Uzbekistan, at approximately 40.1585, 65.3119. Open the interactive map to explore nearby power plants, high-voltage lines and substations.

Ownership

Navoi power station is owned by Navoi Thermal Power Plant JSC. The ultimate parent company is Thermal Power Stations JSC. Across the dataset, Thermal Power Stations JSC is linked to 11 power plants in 2 countries, with 12.5 GW of operating capacity.

Frequently asked questions

What is the capacity of Navoi power station?

Navoi power station has a capacity of 2.15 GW according to the latest Global Energy Monitor data. This figure covers the 13 units or phases listed for the site.

What type of facility is Navoi power station?

Navoi power station is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.

Who owns Navoi power station?

Navoi power station is owned by Navoi Thermal Power Plant JSC. The ultimate parent company is Thermal Power Stations JSC.

Where is Navoi power station located?

It is located in Navoiy, Uzbekistan. Approximate coordinates: 40.1585, 65.3119.

Is Navoi power station operational?

According to the latest data, Navoi power station is in operation. Operating means the facility is built and in commercial service.

When did Navoi power station start operating?

Start year: 1964. Current status: Operating. Its 11 operating units were commissioned between 1964 and 2020. 1 further units or phases are scheduled to come online in 2026.

How much electricity does Navoi power station generate?

Actual output data are not published for every plant. As an indicative estimate, Navoi power station would produce about 7.5 TWh a year, assuming a capacity factor of 40%, which is typical for this technology.

How big is Navoi power station compared with other facilities in Uzbekistan?

Navoi power station ranks #3 by capacity among 17 comparable oil & gas facilities tracked in Uzbekistan.

Latest news on Navoi power station

Other assets of the same owner

Sources and methodology

Source: Global Energy Monitor, Global Integrated Power Tracker, 2026-09 release. Full project profile on GEM.wiki. Last updated: 8 October 2026.

Capacity, status, ownership and unit details come from Global Energy Monitor's public trackers, which are compiled from company reports, government filings and news coverage and updated several times a year. Rankings and shares are calculated by The Daily Energy from the same dataset. Estimated annual generation uses typical capacity factors for each technology and is indicative only.

Data: Global Energy Monitor (GIPT 2026-09, GGIT 2025-11, GOIT 2026-06, GOGET 2026-03, GCMT 2026-08, OSM 2026-10) licensed under CC BY 4.0; transmission grid © OpenStreetMap contributors (ODbL). Compiled and published by The Daily Energy.

Special projects