Overview
Global Energy Monitor tracks 14 units or phases at this site (operating 3.99 GW, under construction 1.40 GW).
Technology: combined cycle, subcritical, supercritical; fuel: natural gas, coal: bituminous, coal: lignite.
Ownership: ENEA Wytwarzanie SP zoo (parent company: ENEA SA).
Its 11 operating units were commissioned between 1972 and 2017. 2 further units or phases are scheduled to come online in 2029. 11 operating units have a planned retirement date, the earliest in 2028.
Why it matters
- The 2nd-largest coal-fired power station in Poland by capacity (of 31 operating coal facilities tracked).
- Provides about 17% of Poland's operating coal capacity and roughly 7.5% of all operating power capacity in the country in the dataset.
- Ranks #64 worldwide among coal facilities of the same status group by capacity.
- At a typical capacity factor of 50% for this technology, it would generate roughly 17 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in Poland
Poland has 23.6 GW of operating coal capacity across 31 plants in the Global Energy Monitor dataset — 44% of the country's total operating power capacity of 53.3 GW.
The coal pipeline in Poland includes 100 MW under construction.
Other major coal plants in Poland include Belchatow power station (5.03 GW), Opole power station (3.33 GW) and Jaworzno power station (2.45 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| CC1, timepoint 1 | 700 MW | Construction | combined cycle | 2029 | |
| CC2, timepoint 1 | 700 MW | Construction | combined cycle | 2029 | |
| Unit 1 | 215 MW | subcritical | 1972 | 2028 | |
| Unit 2 | 225 MW | subcritical | 1973 | 2028 | |
| Unit 3 | 225 MW | subcritical | 1973 | 2028 | |
| Unit 4 | 228 MW | subcritical | 1973 | 2028 | |
| Unit 5 | 225 MW | subcritical | 1973 | 2028 | |
| Unit 6 | 228 MW | subcritical | 1974 | 2028 | |
| Unit 7 | 225 MW | subcritical | 1974 | 2028 | |
| Unit 8 | 228 MW | subcritical | 1975 | 2028 | |
| Unit 9 | 560 MW | subcritical | 1978 | 2041 | |
| Unit 10 | 560 MW | subcritical | 1979 | 2042 | |
| Unit 11 | 1.08 GW | supercritical | 2017 | 2048 | |
| Unit 12 | 1.08 GW | Cancelled | supercritical |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Kozienice power station
Supercritical units operate above the critical pressure of water, reaching efficiencies of roughly 38–42% and lower emissions per megawatt-hour than subcritical units. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Location
Kozienice power station is located in Mazowieckie, Poland, at approximately 51.6673, 21.4613. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Kozienice power station is owned by ENEA Wytwarzanie SP zoo. The ultimate parent company is ENEA SA. Across the dataset, ENEA SA is linked to 10 power plants with 6.16 GW of operating capacity.
Frequently asked questions
What is the capacity of Kozienice power station?
Kozienice power station has a capacity of 3.99 GW according to the latest Global Energy Monitor data. This figure covers the 14 units or phases listed for the site.
What type of facility is Kozienice power station?
Kozienice power station is a coal-fired power station. Supercritical units operate above the critical pressure of water, reaching efficiencies of roughly 38–42% and lower emissions per megawatt-hour than subcritical units.
Who owns Kozienice power station?
Kozienice power station is owned by ENEA Wytwarzanie SP zoo. The ultimate parent company is ENEA SA.
Where is Kozienice power station located?
It is located in Mazowieckie, Poland. Approximate coordinates: 51.6673, 21.4613.
Is Kozienice power station operational?
According to the latest data, Kozienice power station is in operation. Operating means the facility is built and in commercial service.
When did Kozienice power station start operating?
Start year: 1972. Current status: Operating. Its 11 operating units were commissioned between 1972 and 2017. 2 further units or phases are scheduled to come online in 2029. 11 operating units have a planned retirement date, the earliest in 2028.
How much electricity does Kozienice power station generate?
Actual output data are not published for every plant. As an indicative estimate, Kozienice power station would produce about 17 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Kozienice power station compared with other facilities in Poland?
Kozienice power station ranks #2 by capacity among 31 comparable coal facilities tracked in Poland.