Oil & gas · Japan

Himeji Daiichi power station

Himeji Daiichi power station is a 1.44 GW oil- and gas-fired power station located in Hyogo, Japan. The facility is currently in operation, with its first unit entering service in 1995.

1.44 GWCapacity
OperatingStatus
1995Start year
View on the interactive map →

Overview

Global Energy Monitor tracks 5 units or phases at this site (operating 1.44 GW, planned 1.95 GW).

Technology: combined cycle; fuel: LNG.

Ownership: Kansai Electric Power Co.

Its 2 operating units were commissioned between 1995 and 1996. 3 further units or phases are scheduled to come online in 2034.

Why it matters

  • The 23rd-largest oil- and gas-fired power station in Japan by capacity (of 90 operating oil & gas facilities tracked).
  • Provides about 1.5% of Japan's operating oil & gas capacity and roughly 0.6% of all operating power capacity in the country in the dataset.
  • At a typical capacity factor of 40% for this technology, it would generate roughly 5.1 TWh of electricity a year (indicative estimate).

Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.

Oil & gas power in Japan

Japan has 99.2 GW of operating oil & gas capacity across 90 plants in the Global Energy Monitor dataset — 39% of the country's total operating power capacity of 253.7 GW.

The oil & gas pipeline in Japan includes 1.75 GW at earlier planning stages.

Other major oil & gas plants in Japan include Futtsu thermal power station (5.33 GW), Kawagoe thermal power station (4.80 GW) and Chiba thermal power station (4.38 GW).

See the full list: Gas & oil power plants in Japan →

Units and phases

Unit / phaseCapacityStatusTechnologyStartRetired
5 729 MW Operating combined cycle 1995
6 713 MW Operating combined cycle 1996
Repowered unit 1 650 MW Announced combined cycle 2034
Repowered unit 2 650 MW Announced combined cycle 2034
Repowered unit 3 650 MW Announced combined cycle 2034

How gas & oil power plants work

Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.

Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.

Technology at Himeji Daiichi power station

Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.

Location

Imagery © Esri, Maxar, Earthstar Geographics

Himeji Daiichi power station is located in Hyogo, Japan, at approximately 34.7730, 134.6666. Open the interactive map to explore nearby power plants, high-voltage lines and substations.

Ownership

Himeji Daiichi power station is owned by Kansai Electric Power Co. Across the dataset, Kansai Electric Power Co is linked to 76 power plants in 8 countries, with 29.5 GW of operating capacity.

Frequently asked questions

What is the capacity of Himeji Daiichi power station?

Himeji Daiichi power station has a capacity of 1.44 GW according to the latest Global Energy Monitor data. This figure covers the 5 units or phases listed for the site.

What type of facility is Himeji Daiichi power station?

Himeji Daiichi power station is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.

Who owns Himeji Daiichi power station?

Himeji Daiichi power station is owned by Kansai Electric Power Co.

Where is Himeji Daiichi power station located?

It is located in Hyogo, Japan. Approximate coordinates: 34.7730, 134.6666.

Is Himeji Daiichi power station operational?

According to the latest data, Himeji Daiichi power station is in operation. Operating means the facility is built and in commercial service.

When did Himeji Daiichi power station start operating?

Start year: 1995. Current status: Operating. Its 2 operating units were commissioned between 1995 and 1996. 3 further units or phases are scheduled to come online in 2034.

How much electricity does Himeji Daiichi power station generate?

Actual output data are not published for every plant. As an indicative estimate, Himeji Daiichi power station would produce about 5.1 TWh a year, assuming a capacity factor of 40%, which is typical for this technology.

How big is Himeji Daiichi power station compared with other facilities in Japan?

Himeji Daiichi power station ranks #23 by capacity among 90 comparable oil & gas facilities tracked in Japan.

Nearby energy infrastructure

Other assets of the same owner

Sources and methodology

Source: Global Energy Monitor, Global Integrated Power Tracker, 2026-09 release. Full project profile on GEM.wiki. Last updated: 8 October 2026.

Capacity, status, ownership and unit details come from Global Energy Monitor's public trackers, which are compiled from company reports, government filings and news coverage and updated several times a year. Rankings and shares are calculated by The Daily Energy from the same dataset. Estimated annual generation uses typical capacity factors for each technology and is indicative only.

Data: Global Energy Monitor (GIPT 2026-09, GGIT 2025-11, GOIT 2026-06, GOGET 2026-03, GCMT 2026-08, OSM 2026-10) licensed under CC BY 4.0; transmission grid © OpenStreetMap contributors (ODbL). Compiled and published by The Daily Energy.

Special projects