US Energy Department Offers $2.8 Billion Loan for Wyoming Grid Interconnection

US Energy Department Offers $2.8 Billion Loan for Wyoming Grid Interconnection
Summary not found.

The US Department of Energy’s Office of Energy Dominance Financing said on November 17 that it has issued a conditional loan commitment of up to $2.8 billion for Grid United’s Wyoming Intertie transmission project. The department says the line would add approximately 1.8 gigawatts (GW) of electricity transfer capacity between two of the country’s major grid regions.

The commitment is not a final award. According to the Department of Energy, Grid United’s project still has to satisfy a set of technical, legal, environmental and financial conditions before the department will enter into a definitive financing agreement, a standard structure for conditional commitments issued through its loan programs.

Doubling a Thin Seam Between Grids

The Wyoming Intertie is designed to link the footprint of the Southwest Power Pool (SPP) with the Western Electricity Coordinating Council (WECC) region, the two grid operating areas that meet across the western United States. The department says the project would roughly double the existing transfer capacity between SPP and WECC. Transmission planners have long treated the broader seam between the country’s Eastern and Western Interconnections as a bottleneck served by only a handful of direct-current ties with limited combined capacity, a constraint that has drawn growing attention as both regions add wind, solar and data-centre load at different paces.

The Department of Energy estimates the added transfer capacity could save consumers up to $39 billion across 17 Western states, a figure the department attributes to the project’s ability to move power between regions with different generation mixes and demand patterns, reducing the need for more expensive local generation or curtailment on either side of the line.

The Wyoming Intertie is one of several projects aimed at strengthening connections across the historically thin Eastern-Western Interconnection seam. SPP itself has been expanding westward in recent years, and other developers have proposed separate high-voltage direct-current lines, including the Three Corners Connector, to link SPP and WECC territory more directly. Large transmission build-outs aimed at moving renewable power over long distances are not unique to the United States: India recently approved a $7.3 billion ultra-high-voltage line to move solar and wind power eastward across the country, and Britain’s National Grid has been raising transmission capital spending to keep pace with new generation and demand. The Department of Energy’s loan programs have previously backed transmission projects such as the Wyoming-linked lines and interregional ties elsewhere in the country, part of a broader federal push to fund transmission that individual utilities have been reluctant to build alone because the benefits cross multiple utility and state jurisdictions.

The loan programme behind the Wyoming Intertie commitment has backed large transmission deals before: the Department of Energy announced roughly $1.3 billion in loans for three separate large-scale transmission projects in 2024, part of a broader pattern of federal financing stepping in where individual utilities have been reluctant to build interregional lines alone. Separately, SPP itself reached a milestone in its own westward expansion in April 2026, becoming, according to grid-services provider OATI, the first regional transmission organisation in US history to operate across both the Eastern and Western Interconnections, though that organisational expansion is distinct from the physical Wyoming Intertie line now seeking financing.

What Comes Next

Grid United has not published a construction timeline or in-service date for the Wyoming Intertie, and the Department of Energy’s announcement does not specify how long the conditions attached to the loan are expected to take to satisfy. The department’s $39 billion savings estimate is its own modelling output tied to the proposed capacity addition, not an independently audited figure, and should be read as a projection rather than a confirmed outcome.

Sources

  • US Department of Energy, “Energy Department Announces $2.8 Billion Loan to Strengthen Grid Reliability and Help Lower Costs in Wyoming,” November 17, 2026, for the loan terms, capacity figures and savings estimate.
  • Public Power Association, reporting on the Office of Energy Dominance Financing’s conditional commitment, for programme context.

Illustrative image. Photo: Frans Berkelaar, CC BY 2.0, via Wikimedia Commons — source