Global Energy Monitor tracks 6 units or phases at this site (operating 1.66 GW, planned 600 MW).
Technology: steam turbine, unknown, combined cycle, subcritical; fuel: heavy fuel oil, fossil liquids: crude oil, heavy fuel oil, fossil liquids: crude oil, fossil gas: LNG, LNG, coal: bituminous.
Ownership: Hokuriku Electric Power Co.
Its 5 operating units were commissioned between 1971 and 2018. 1 further units or phases are scheduled to come online in 2033. 1 operating units have a planned retirement date, the earliest in 2028.
Why it matters
- The 20th-largest oil- and gas-fired power station in Japan by capacity (of 90 operating oil & gas facilities tracked).
- Provides about 1.7% of Japan's operating oil & gas capacity and roughly 0.7% of all operating power capacity in the country in the dataset.
- At a typical capacity factor of 40% for this technology, it would generate roughly 5.8 TWh of electricity a year (indicative estimate).
Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.
Oil & gas power in Japan
Japan has 99.2 GW of operating oil & gas capacity across 90 plants in the Global Energy Monitor dataset — 39% of the country's total operating power capacity of 253.7 GW.
The oil & gas pipeline in Japan includes 1.75 GW at earlier planning stages.
Other major oil & gas plants in Japan include Futtsu thermal power station (5.33 GW), Kawagoe thermal power station (4.80 GW) and Chiba thermal power station (4.38 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| 1 | 240 MW | steam turbine | 1974 | ||
| 2 | 500 MW | steam turbine | 1981 | ||
| 3 | 600 MW | Pre-construction | unknown | 2033 | |
| CC 1 | 425 MW | combined cycle | 2018 | ||
| Unit 1 | 250 MW | subcritical | 1971 | 2028 | |
| Unit 2 | 250 MW | subcritical | 1972 |
How gas & oil power plants work
Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.
Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.
Technology at Toyama Shinko power station
Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant. Steam-turbine units burn fuel in a boiler to raise steam; they are generally older and less flexible than combined-cycle plants.
Location
Toyama Shinko power station is located in Toyama, Japan, at approximately 36.7657, 137.1287. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Toyama Shinko power station is owned by Hokuriku Electric Power Co. Across the dataset, Hokuriku Electric Power Co is linked to 21 power plants with 5.65 GW of operating capacity.
Frequently asked questions
What is the capacity of Toyama Shinko power station?
Toyama Shinko power station has a capacity of 1.66 GW according to the latest Global Energy Monitor data. This figure covers the 6 units or phases listed for the site.
What type of facility is Toyama Shinko power station?
Toyama Shinko power station is a oil- and gas-fired power station. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Who owns Toyama Shinko power station?
Toyama Shinko power station is owned by Hokuriku Electric Power Co.
Where is Toyama Shinko power station located?
It is located in Toyama, Japan. Approximate coordinates: 36.7657, 137.1287.
Is Toyama Shinko power station operational?
According to the latest data, Toyama Shinko power station is in operation. Operating means the facility is built and in commercial service.
When did Toyama Shinko power station start operating?
Start year: 1971. Current status: Operating. Its 5 operating units were commissioned between 1971 and 2018. 1 further units or phases are scheduled to come online in 2033. 1 operating units have a planned retirement date, the earliest in 2028.
How much electricity does Toyama Shinko power station generate?
Actual output data are not published for every plant. As an indicative estimate, Toyama Shinko power station would produce about 5.8 TWh a year, assuming a capacity factor of 40%, which is typical for this technology.
How big is Toyama Shinko power station compared with other facilities in Japan?
Toyama Shinko power station ranks #20 by capacity among 90 comparable oil & gas facilities tracked in Japan.