Overview
Global Energy Monitor tracks 10 units or phases at this site (under construction 2.25 GW, retired 2.25 GW).
Technology: unknown, subcritical, steam turbine; fuel: coal: unknown, coal: bituminous, natural gas.
Ownership: Israel Electric Corp Ltd (parent company: Government of Israel; unknown).
4 further units or phases are scheduled to come online in 2026. 4 units have already been retired (2022–2025).
Why it matters
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in Israel
The coal pipeline in Israel includes 2.25 GW under construction.
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Project D Unit 1 | 630 MW | Cancelled | unknown | ||
| Project D Unit 2 | 630 MW | Cancelled | unknown | ||
| Unit 1, timepoint 1 | 575 MW | Retired | subcritical | 1991 | 2022 |
| Unit 1, timepoint 2 | 575 MW | Construction | steam turbine | 2026 | |
| Unit 2, timepoint 1 | 575 MW | Retired | subcritical | 1990 | 2025 |
| Unit 2, timepoint 2 | 575 MW | Construction | steam turbine | 2026 | |
| Unit 3, timepoint 1 | 550 MW | Retired | subcritical | 2001 | 2025 |
| Unit 3, timepoint 2 | 550 MW | Construction | steam turbine | 2026 | |
| Unit 4, timepoint 1 | 550 MW | Retired | subcritical | 2000 | 2025 |
| Unit 4, timepoint 2 | 550 MW | Construction | steam turbine | 2026 |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Rutenberg power station
Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity. Steam-turbine units burn fuel in a boiler to raise steam; they are generally older and less flexible than combined-cycle plants.
Location
Rutenberg power station is located in HaDarom, Israel, at approximately 31.6307, 34.5202. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Rutenberg power station is owned by Israel Electric Corp Ltd. The ultimate parent company is Government of Israel; unknown. Across the dataset, Government of Israel is linked to 9 power plants with 8.27 GW of operating capacity.
Frequently asked questions
What is the capacity of Rutenberg power station?
Rutenberg power station has a capacity of 2.25 GW according to the latest Global Energy Monitor data. This figure covers the 10 units or phases listed for the site.
What type of facility is Rutenberg power station?
Rutenberg power station is a coal-fired power station. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Who owns Rutenberg power station?
Rutenberg power station is owned by Israel Electric Corp Ltd. The ultimate parent company is Government of Israel; unknown.
Where is Rutenberg power station located?
It is located in HaDarom, Israel. Approximate coordinates: 31.6307, 34.5202.
Is Rutenberg power station operational?
According to the latest data, Rutenberg power station is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.
When is Rutenberg power station expected to start?
Start year: 1990. Current status: Construction. 4 further units or phases are scheduled to come online in 2026. 4 units have already been retired (2022–2025).