Oil & gas · Qatar

Ras Abu Fontas (E) power plant

Ras Abu Fontas (E) power plant is a 2.42 GW oil- and gas-fired power station located in Wakra, Qatar. The facility is currently under construction, with a targeted start date of 2028.

2.42 GWCapacity (all phases)
ConstructionStatus
2028Start year
View on the interactive map →

Overview

Global Energy Monitor tracks 3 units or phases at this site (under construction 2.42 GW).

Technology: combined cycle; fuel: natural gas.

Ownership: Nebras Energy QPSC.

3 further units or phases are scheduled to come online in 2028–2029.

Why it matters

  • The 3rd-largest oil- and gas-fired power station in Qatar by capacity (of 12 operating, under-construction and planned oil & gas facilities tracked).
  • If completed, it would add 2.42 GW to Qatar's oil & gas fleet — equivalent to 19% of today's operating oil & gas capacity.

Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.

Oil & gas power in Qatar

Qatar has 12.6 GW of operating oil & gas capacity across 10 plants in the Global Energy Monitor dataset — 88% of the country's total operating power capacity of 14.3 GW.

The oil & gas pipeline in Qatar includes 2.92 GW under construction.

Other major oil & gas plants in Qatar include Ras Laffan C power plant (2.73 GW), Umm Al Houl power plant (2.52 GW) and Mesaieed CCGT power station (2.01 GW).

See the full list: Gas & oil power plants in Qatar →

Units and phases

Unit / phaseCapacityStatusTechnologyStartRetired
New-Phase 1 836 MW Construction combined cycle 2028
New-Phase 2 790 MW Construction combined cycle 2029
New-Phase 3 790 MW Construction combined cycle 2029

How gas & oil power plants work

Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.

Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.

Technology at Ras Abu Fontas (E) power plant

Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.

Location

Location is approximate. Imagery © Esri, Maxar, Earthstar Geographics

Ras Abu Fontas (E) power plant is located in Wakra, Qatar, at approximately 24.8471, 51.3037. Open the interactive map to explore nearby power plants, high-voltage lines and substations.

Ownership

Ras Abu Fontas (E) power plant is owned by Nebras Energy QPSC. Across the dataset, Nebras Energy QPSC is linked to 17 power plants in 7 countries, with 16.1 GW of operating capacity.

Frequently asked questions

What is the capacity of Ras Abu Fontas (E) power plant?

Ras Abu Fontas (E) power plant has a capacity of 2.42 GW according to the latest Global Energy Monitor data. This figure covers the 3 units or phases listed for the site.

What type of facility is Ras Abu Fontas (E) power plant?

Ras Abu Fontas (E) power plant is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.

Who owns Ras Abu Fontas (E) power plant?

Ras Abu Fontas (E) power plant is owned by Nebras Energy QPSC.

Where is Ras Abu Fontas (E) power plant located?

It is located in Wakra, Qatar. Approximate coordinates: 24.8471, 51.3037.

Is Ras Abu Fontas (E) power plant operational?

According to the latest data, Ras Abu Fontas (E) power plant is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.

When is Ras Abu Fontas (E) power plant expected to start?

Start year: 2028. Current status: Construction. 3 further units or phases are scheduled to come online in 2028–2029.

How big is Ras Abu Fontas (E) power plant compared with other facilities in Qatar?

Ras Abu Fontas (E) power plant ranks #3 by capacity among 12 comparable oil & gas facilities tracked in Qatar.

Nearby energy infrastructure

Other assets of the same owner

Sources and methodology

Source: Global Energy Monitor, Global Integrated Power Tracker, 2026-09 release. Full project profile on GEM.wiki. Last updated: 8 October 2026.

Capacity, status, ownership and unit details come from Global Energy Monitor's public trackers, which are compiled from company reports, government filings and news coverage and updated several times a year. Rankings and shares are calculated by The Daily Energy from the same dataset. Estimated annual generation uses typical capacity factors for each technology and is indicative only.

Data: Global Energy Monitor (GIPT 2026-09, GGIT 2025-11, GOIT 2026-06, GOGET 2026-03, GCMT 2026-08, OSM 2026-10) licensed under CC BY 4.0; transmission grid © OpenStreetMap contributors (ODbL). Compiled and published by The Daily Energy.