Overview
Global Energy Monitor tracks 6 units or phases at this site (operating 1.20 GW, planned 1.32 GW).
Technology: subcritical, unknown; fuel: coal: anthracite.
Ownership: Cpi Guizhou Jinyuan Group Co Ltd (parent company: State Power Investment Corp Ltd; Guizhou Panjiang Investment Holding (Group) Co Ltd; Guizhou Qiansheng State-Owned Assets Management Co Ltd; natural…).
Its 4 operating units were commissioned between 2005 and 2006.
Why it matters
- At a typical capacity factor of 50% for this technology, it would generate roughly 5.3 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in China
China has 1,259.6 GW of operating coal capacity across 1,188 plants in the Global Energy Monitor dataset — 41% of the country's total operating power capacity of 3,086.2 GW.
The coal pipeline in China includes 93.1 GW under construction and 145.8 GW at earlier planning stages.
Other major coal plants in China include Beilun power station (7.10 GW), Pingwei power station (6.54 GW) and Togtoh power station (6.12 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Phase II Unit 1 | 300 MW | subcritical | 2005 | ||
| Phase II Unit 2 | 300 MW | subcritical | 2005 | ||
| Phase II Unit 3 | 300 MW | subcritical | 2006 | ||
| Phase II Unit 4 | 300 MW | subcritical | 2006 | ||
| Phase III Unit 1 | 660 MW | Announced | unknown | ||
| Phase III Unit 2 | 660 MW | Announced | unknown |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Nayong-2 power station
Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Location
Nayong-2 power station is located in Guizhou, China, at approximately 26.5998, 105.2024. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Nayong-2 power station is owned by Cpi Guizhou Jinyuan Group Co Ltd. The ultimate parent company is State Power Investment Corp Ltd; Guizhou Panjiang Investment Holding (Group) Co Ltd; Guizhou Qiansheng State-Owned Assets Management Co Ltd; natural person(s); unknown. Across the dataset, State Power Investment Corp Ltd is linked to 163 power plants in 5 countries, with 82.9 GW of operating capacity.
Frequently asked questions
What is the capacity of Nayong-2 power station?
Nayong-2 power station has a capacity of 1.20 GW according to the latest Global Energy Monitor data. This figure covers the 6 units or phases listed for the site.
What type of facility is Nayong-2 power station?
Nayong-2 power station is a coal-fired power station. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Who owns Nayong-2 power station?
Nayong-2 power station is owned by Cpi Guizhou Jinyuan Group Co Ltd. The ultimate parent company is State Power Investment Corp Ltd; Guizhou Panjiang Investment Holding (Group) Co Ltd; Guizhou Qiansheng State-Owned Assets Management Co Ltd; natural person(s); unknown.
Where is Nayong-2 power station located?
It is located in Guizhou, China. Approximate coordinates: 26.5998, 105.2024.
Is Nayong-2 power station operational?
According to the latest data, Nayong-2 power station is in operation. Operating means the facility is built and in commercial service.
When did Nayong-2 power station start operating?
Start year: 2005. Current status: Operating. Its 4 operating units were commissioned between 2005 and 2006.
How much electricity does Nayong-2 power station generate?
Actual output data are not published for every plant. As an indicative estimate, Nayong-2 power station would produce about 5.3 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Nayong-2 power station compared with other facilities in China?
Nayong-2 power station ranks #397 by capacity among 1188 comparable coal facilities tracked in China.