Overview
GEM tracks 4 units or phases at this site (operating 1.20 GW).
Technology: subcritical; fuel: coal: anthracite.
Ownership: Cpi Guizhou Jinyuan Group Co Ltd (parent company: State Power Investment Corp Ltd; Guizhou Panjiang Investment Holding (Group) Co Ltd; Guizhou Qiansheng State-Owned Assets Management Co Ltd; natural…).
Why it matters
- Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Phase I Unit 1 | 300 MW | subcritical | 2003 | ||
| Phase I Unit 2 | 300 MW | subcritical | 2003 | ||
| Phase I Unit 3 | 300 MW | subcritical | 2004 | ||
| Phase I Unit 4 | 300 MW | subcritical | 2004 |
Location
Frequently asked questions
What is the capacity of Nayong-1 power station?
Nayong-1 power station has a capacity of 1.20 GW according to the latest Global Energy Monitor data.
Who owns Nayong-1 power station?
Cpi Guizhou Jinyuan Group Co Ltd — parent company: State Power Investment Corp Ltd; Guizhou Panjiang Investment Holding (Group) Co Ltd; Guizhou Qiansheng State-Owned Assets Management Co Ltd; natural person(s); unknown.
Where is Nayong-1 power station located?
It is located in Guizhou, China. Approximate coordinates: 26.6526, 105.1823.
When did Nayong-1 power station start operating?
Start year: 2003. Current status: Operating.