Nuclear · Japan

Genkai nuclear power plant

Genkai nuclear power plant is a 2.36 GW nuclear power plant located in Saga, Japan. The facility is currently in operation, with its first unit entering service in 1994.

2.36 GWCapacity
OperatingStatus
1994Start year
View on the interactive map →

Overview

Global Energy Monitor tracks 4 units or phases at this site (operating 2.36 GW, retired 1.12 GW).

Technology: pressurized water reactor.

Ownership: Kyushu Electric Power Co Inc.

Its 2 operating units were commissioned between 1994 and 1997. 2 units have already been retired (2015–2019).

Why it matters

  • The 2nd-largest nuclear power plant in Japan by capacity (of 9 operating nuclear facilities tracked).
  • Provides about 16% of Japan's operating nuclear capacity and roughly 0.9% of all operating power capacity in the country in the dataset.
  • Ranks #73 worldwide among nuclear facilities of the same status group by capacity.
  • At a typical capacity factor of 85% for this technology, it would generate roughly 18 TWh of electricity a year (indicative estimate).

Nuclear plants supply large volumes of low-carbon baseload electricity with very high capacity factors, so a single station can cover a significant share of national demand.

Nuclear power in Japan

Japan has 14.6 GW of operating nuclear capacity across 9 plants in the Global Energy Monitor dataset — 5.8% of the country's total operating power capacity of 253.7 GW.

The nuclear pipeline in Japan includes 4.55 GW under construction.

Other major nuclear plants in Japan include Takahama nuclear power plant (3.39 GW), Ohi nuclear power plant (2.36 GW) and Tomari nuclear power plant (2.07 GW).

See the full list: Nuclear power plants in Japan →

Units and phases

Unit / phaseCapacityStatusTechnologyStartRetired
1 559 MW Retired pressurized water reactor 1975 2015
2 559 MW Retired pressurized water reactor 1981 2019
3 1.18 GW Operating pressurized water reactor 1994
4 1.18 GW Operating pressurized water reactor 1997

How nuclear power plants work

A nuclear power plant uses heat from controlled fission of uranium (or plutonium) fuel in a reactor core to produce steam, which drives a turbine-generator in the same way as a thermal power station. The reactor is surrounded by multiple safety barriers and a containment building.

Nuclear units typically run more than 90% of the hours in a year, so a single large reactor can supply several terawatt-hours of almost carbon-free electricity annually. Construction times are long and capital costs high, but fuel costs are low and plants are often licensed to operate for 60 years or more.

Technology at Genkai nuclear power plant

Pressurised water reactors (PWR), the most common reactor type worldwide, keep the primary coolant under high pressure and transfer its heat to a separate steam circuit.

Location

Imagery © Esri, Maxar, Earthstar Geographics

Genkai nuclear power plant is located in Saga, Japan, at approximately 33.5152, 129.8360. Open the interactive map to explore nearby power plants, high-voltage lines and substations.

Ownership

Genkai nuclear power plant is owned by Kyushu Electric Power Co Inc. Across the dataset, Kyushu Electric Power Co Inc is linked to 47 power plants in 7 countries, with 22.1 GW of operating capacity.

Frequently asked questions

What is the capacity of Genkai nuclear power plant?

Genkai nuclear power plant has a capacity of 2.36 GW according to the latest Global Energy Monitor data. This figure covers the 4 units or phases listed for the site.

What type of facility is Genkai nuclear power plant?

Genkai nuclear power plant is a nuclear power plant. Pressurised water reactors (PWR), the most common reactor type worldwide, keep the primary coolant under high pressure and transfer its heat to a separate steam circuit.

Who owns Genkai nuclear power plant?

Genkai nuclear power plant is owned by Kyushu Electric Power Co Inc.

Where is Genkai nuclear power plant located?

It is located in Saga, Japan. Approximate coordinates: 33.5152, 129.8360.

Is Genkai nuclear power plant operational?

According to the latest data, Genkai nuclear power plant is in operation. Operating means the facility is built and in commercial service.

When did Genkai nuclear power plant start operating?

Start year: 1994. Current status: Operating. Its 2 operating units were commissioned between 1994 and 1997. 2 units have already been retired (2015–2019).

How much electricity does Genkai nuclear power plant generate?

Actual output data are not published for every plant. As an indicative estimate, Genkai nuclear power plant would produce about 18 TWh a year, assuming a capacity factor of 85%, which is typical for this technology.

How big is Genkai nuclear power plant compared with other facilities in Japan?

Genkai nuclear power plant ranks #2 by capacity among 9 comparable nuclear facilities tracked in Japan.

Nearby energy infrastructure

Other assets of the same owner

Sources and methodology

Source: Global Energy Monitor, Global Integrated Power Tracker, 2026-09 release. Full project profile on GEM.wiki. Last updated: 8 October 2026.

Capacity, status, ownership and unit details come from Global Energy Monitor's public trackers, which are compiled from company reports, government filings and news coverage and updated several times a year. Rankings and shares are calculated by The Daily Energy from the same dataset. Estimated annual generation uses typical capacity factors for each technology and is indicative only.

Data: Global Energy Monitor (GIPT 2026-09, GGIT 2025-11, GOIT 2026-06, GOGET 2026-03, GCMT 2026-08, OSM 2026-10) licensed under CC BY 4.0; transmission grid © OpenStreetMap contributors (ODbL). Compiled and published by The Daily Energy.

Special projects