CP2 LNG Terminal power station is a 2.19 GW oil- and gas-fired power station located in Louisiana, United States. The facility is currently under construction, with a targeted start date of 2029.

2.19 GWCapacity (all phases)
ConstructionStatus
2029Start year
View on the interactive map →

Overview

Global Energy Monitor tracks 3 units or phases at this site (under construction 1.47 GW, planned 720 MW).

Technology: combined cycle, unknown; fuel: natural gas.

Ownership: Venture Global CP2 LNG LLC (parent company: Venture Global Holdings Inc).

2 further units or phases are scheduled to come online in 2029–2030.

Why it matters

Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.

Oil & gas power in United States

United States has 590.9 GW of operating oil & gas capacity across 1,106 plants in the Global Energy Monitor dataset — 46% of the country's total operating power capacity of 1,280.9 GW.

The oil & gas pipeline in United States includes 29.4 GW under construction and 257.6 GW at earlier planning stages.

Other major oil & gas plants in United States include West County energy center (4.26 GW), Bruce Mansfield power station (3.64 GW) and Crystal River Energy Complex (3.45 GW).

See the full list: Gas & oil power plants in United States →

Units and phases

Unit / phaseCapacityStatusTechnologyStartRetired
Phase 1 750 MW Construction combined cycle 2029
Phase 2 720 MW Construction combined cycle 2030
Phase 3 720 MW Pre-construction unknown

How gas & oil power plants work

Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.

Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.

Technology at CP2 LNG Terminal power station

Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.

Location

Imagery © Esri, Maxar, Earthstar Geographics

CP2 LNG Terminal power station is located in Louisiana, United States, at approximately 29.7743, -93.3239. Open the interactive map to explore nearby power plants, high-voltage lines and substations.

Ownership

CP2 LNG Terminal power station is owned by Venture Global CP2 LNG LLC. The ultimate parent company is Venture Global Holdings Inc. Across the dataset, Venture Global Holdings Inc is linked to 3 power plants with 1.44 GW of operating capacity.

Frequently asked questions

What is the capacity of CP2 LNG Terminal power station?

CP2 LNG Terminal power station has a capacity of 2.19 GW according to the latest Global Energy Monitor data. This figure covers the 3 units or phases listed for the site.

What type of facility is CP2 LNG Terminal power station?

CP2 LNG Terminal power station is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.

Who owns CP2 LNG Terminal power station?

CP2 LNG Terminal power station is owned by Venture Global CP2 LNG LLC. The ultimate parent company is Venture Global Holdings Inc.

Where is CP2 LNG Terminal power station located?

It is located in Louisiana, United States. Approximate coordinates: 29.7743, -93.3239.

Is CP2 LNG Terminal power station operational?

According to the latest data, CP2 LNG Terminal power station is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.

When is CP2 LNG Terminal power station expected to start?

Start year: 2029. Current status: Construction. 2 further units or phases are scheduled to come online in 2029–2030.

How big is CP2 LNG Terminal power station compared with other facilities in United States?

CP2 LNG Terminal power station ranks #43 by capacity among 1399 comparable oil & gas facilities tracked in United States.

Nearby energy infrastructure

Other assets of the same owner

Sources and methodology

Source: Global Energy Monitor, Global Integrated Power Tracker, 2026-09 release. Full project profile on GEM.wiki. Last updated: 8 October 2026.

Capacity, status, ownership and unit details come from Global Energy Monitor's public trackers, which are compiled from company reports, government filings and news coverage and updated several times a year. Rankings and shares are calculated by The Daily Energy from the same dataset. Estimated annual generation uses typical capacity factors for each technology and is indicative only.

Data: Global Energy Monitor (GIPT 2026-09, GGIT 2025-11, GOIT 2026-06, GOGET 2026-03, GCMT 2026-08, OSM 2026-10) licensed under CC BY 4.0; transmission grid © OpenStreetMap contributors (ODbL). Compiled and published by The Daily Energy.

Special projects