Overview
Global Energy Monitor tracks 12 units or phases at this site (operating 3.34 GW, planned 785 MW, retired 982 MW).
Technology: subcritical, steam turbine, supercritical, combined cycle; fuel: coal: bituminous, natural gas.
Ownership: Alabama Power Co (parent company: Southern Co).
Its 7 operating units were commissioned between 1971 and 2023. 1 further units or phases are scheduled to come online in 2028. 4 units have already been retired (2015–2022). 1 operating units have a planned retirement date, the earliest in 2028.
Why it matters
- The 3rd-largest coal-fired power station in United States by capacity (of 181 operating coal facilities tracked).
- Provides about 2% of United States's operating coal capacity.
- Ranks #87 worldwide among coal facilities of the same status group by capacity.
- At a typical capacity factor of 50% for this technology, it would generate roughly 15 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in United States
United States has 167.4 GW of operating coal capacity across 181 plants in the Global Energy Monitor dataset — 13% of the country's total operating power capacity of 1,280.9 GW.
The coal pipeline in United States includes 6.24 GW under construction and 6.81 GW at earlier planning stages.
Other major coal plants in United States include Homer City Generating Station (4.71 GW), Parish Generating Station (3.95 GW) and Plant Bowen (3.50 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Unit 1, timepoint 1 | 153 MW | Retired | subcritical | 1954 | 2015 |
| Unit 1, timepoint 2 | 153 MW | steam turbine | 2015 | ||
| Unit 2, timepoint 1 | 153 MW | Retired | subcritical | 1954 | 2015 |
| Unit 2, timepoint 2 | 153 MW | steam turbine | 2015 | ||
| Unit 3 | 272 MW | Retired | subcritical | 1959 | 2015 |
| Unit 4, timepoint 1 | 404 MW | Retired | subcritical | 1969 | 2022 |
| Unit 4, timepoint 2 | 404 MW | steam turbine | 2022 | ||
| Unit 5 | 789 MW | supercritical | 1971 | 2028 | |
| Unit 5, timepoint 2 | 785 MW | Pre-construction | steam turbine | 2028 | |
| Unit 6 | 535 MW | combined cycle | 2000 | ||
| Unit 7 | 535 MW | combined cycle | 2000 | ||
| Unit 8 | 774 MW | combined cycle | 2023 |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Barry Steam Plant
Supercritical units operate above the critical pressure of water, reaching efficiencies of roughly 38–42% and lower emissions per megawatt-hour than subcritical units. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Location
Barry Steam Plant is located in Alabama, United States, at approximately 31.0066, -88.0088. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Barry Steam Plant is owned by Alabama Power Co. The ultimate parent company is Southern Co. Across the dataset, Southern Co is linked to 43 power plants with 37.8 GW of operating capacity.
Frequently asked questions
What is the capacity of Barry Steam Plant?
Barry Steam Plant has a capacity of 3.34 GW according to the latest Global Energy Monitor data. This figure covers the 12 units or phases listed for the site.
What type of facility is Barry Steam Plant?
Barry Steam Plant is a coal-fired power station. Supercritical units operate above the critical pressure of water, reaching efficiencies of roughly 38–42% and lower emissions per megawatt-hour than subcritical units.
Who owns Barry Steam Plant?
Barry Steam Plant is owned by Alabama Power Co. The ultimate parent company is Southern Co.
Where is Barry Steam Plant located?
It is located in Alabama, United States. Approximate coordinates: 31.0066, -88.0088.
Is Barry Steam Plant operational?
According to the latest data, Barry Steam Plant is in operation. Operating means the facility is built and in commercial service.
When did Barry Steam Plant start operating?
Start year: 1971. Current status: Operating. Its 7 operating units were commissioned between 1971 and 2023. 1 further units or phases are scheduled to come online in 2028. 4 units have already been retired (2015–2022). 1 operating units have a planned retirement date, the earliest in 2028.
How much electricity does Barry Steam Plant generate?
Actual output data are not published for every plant. As an indicative estimate, Barry Steam Plant would produce about 15 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Barry Steam Plant compared with other facilities in United States?
Barry Steam Plant ranks #3 by capacity among 181 comparable coal facilities tracked in United States.