Abuja power station is a 1.25 GW oil- and gas-fired power station located in Abuja Federal Capital Territory, Nigeria. The facility is currently under construction, with a targeted start date of 2037.

1.25 GWCapacity (all phases)
ConstructionStatus
2037Start year
View on the interactive map →

Overview

Global Energy Monitor tracks 3 units or phases at this site (under construction 900 MW, planned 350 MW).

Technology: combined cycle; fuel: natural gas.

Ownership: NNPC Ltd; General Electric Co; China Machinery Engineering Corp (parent company: China National Machinery Industry Corp; General Electric Co; NNPC Ltd).

2 further units or phases are scheduled to come online in 2037.

Why it matters

  • The 5th-largest oil- and gas-fired power station in Nigeria by capacity (of 42 operating, under-construction and planned oil & gas facilities tracked).
  • If completed, it would add 1.25 GW to Nigeria's oil & gas fleet — equivalent to 11% of today's operating oil & gas capacity.

Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.

Oil & gas power in Nigeria

Nigeria has 11.0 GW of operating oil & gas capacity across 25 plants in the Global Energy Monitor dataset — 77% of the country's total operating power capacity of 14.4 GW.

The oil & gas pipeline in Nigeria includes 1.76 GW under construction and 9.54 GW at earlier planning stages.

Other major oil & gas plants in Nigeria include Egbin power station (1.32 GW).

See the full list: Gas & oil power plants in Nigeria →

Units and phases

Unit / phaseCapacityStatusTechnologyStartRetired
1 350 MW Pre-construction combined cycle
2 450 MW Construction combined cycle 2037
3 450 MW Construction combined cycle 2037

How gas & oil power plants work

Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.

Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.

Technology at Abuja power station

Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.

Location

Location is approximate. Imagery © Esri, Maxar, Earthstar Geographics

Abuja power station is located in Abuja Federal Capital Territory, Nigeria, at approximately 8.9397, 7.0768. Open the interactive map to explore nearby power plants, high-voltage lines and substations.

Ownership

Abuja power station is owned by NNPC Ltd; General Electric Co; China Machinery Engineering Corp. The ultimate parent company is China National Machinery Industry Corp; General Electric Co; NNPC Ltd. Across the dataset, China National Machinery Industry Corp is linked to 12 power plants in 4 countries, with 3.62 GW of operating capacity.

Frequently asked questions

What is the capacity of Abuja power station?

Abuja power station has a capacity of 1.25 GW according to the latest Global Energy Monitor data. This figure covers the 3 units or phases listed for the site.

What type of facility is Abuja power station?

Abuja power station is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.

Who owns Abuja power station?

Abuja power station is owned by NNPC Ltd; General Electric Co; China Machinery Engineering Corp. The ultimate parent company is China National Machinery Industry Corp; General Electric Co; NNPC Ltd.

Where is Abuja power station located?

It is located in Abuja Federal Capital Territory, Nigeria. Approximate coordinates: 8.9397, 7.0768.

Is Abuja power station operational?

According to the latest data, Abuja power station is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.

When is Abuja power station expected to start?

Start year: 2037. Current status: Construction. 2 further units or phases are scheduled to come online in 2037.

How big is Abuja power station compared with other facilities in Nigeria?

Abuja power station ranks #5 by capacity among 42 comparable oil & gas facilities tracked in Nigeria.

Latest news on Abuja power station

Sources and methodology

Source: Global Energy Monitor, Global Integrated Power Tracker, 2026-09 release. Full project profile on GEM.wiki. Last updated: 8 October 2026.

Capacity, status, ownership and unit details come from Global Energy Monitor's public trackers, which are compiled from company reports, government filings and news coverage and updated several times a year. Rankings and shares are calculated by The Daily Energy from the same dataset. Estimated annual generation uses typical capacity factors for each technology and is indicative only.

Data: Global Energy Monitor (GIPT 2026-09, GGIT 2025-11, GOIT 2026-06, GOGET 2026-03, GCMT 2026-08, OSM 2026-10) licensed under CC BY 4.0; transmission grid © OpenStreetMap contributors (ODbL). Compiled and published by The Daily Energy.

Special projects