Country profile

Algeria energy infrastructure

Global Energy Monitor tracks 278 energy facilities in Algeria, including power plants with 28.4 GW of operating generating capacity. A further 5.06 GW is under construction and 1.59 GW is in planning stages.

28.4 GWOperating power capacity
5.06 GWUnder construction
278Facilities tracked
Explore Algeria on the map →

Algeria's energy system at a glance

Algeria has 28.4 GW of operating power generation capacity across 93 plants in the Global Energy Monitor dataset. Oil & gas is the largest source, with 27.7 GW or 98% of the total. It is followed by solar (1.6%) and hydropower (0.7%).

Low-carbon sources — nuclear, hydropower, wind, solar, geothermal and bioenergy — make up 2.3% of operating capacity, while coal, oil and gas account for 98%. Wind and solar alone represent 1.6%.

A further 5.06 GW of generating capacity is under construction, led by solar (2.84 GW). Another 1.59 GW is announced, proposed or in pre-construction.

Beyond power generation, the map covers 46 gas pipeline projects (about 17,889 km in operation), 34 oil and NGL pipelines, 2 LNG terminals (25.3 mtpa export capacity in operation) and 54 oil and gas fields (47 producing) in Algeria.

Operating power capacity by technology

TechnologyOperatingPlants operatingUnder constructionPlanned
Oil & gas27.7 GW542.22 GW—
Solar451 MW352.84 GW1.59 GW
Hydropower196 MW3——
Wind10 MW1——

Largest power plants in Algeria

#NameTypeCapacityStatusStart
1Ras Djinet power plantBoumerdèsOil & gas1.87 GWOperating1986
2Oumache power stationBiskraOil & gas1.46 GWOperating2016
3Bellara power stationJijelOil & gas1.40 GWOperating2022
4Kais power stationKhenchelaOil & gas1.27 GWOperating2019
5Hadjret En Nouss power plantTipazaOil & gas1.23 GWOperating2009
6Djelfa power stationDjelfaOil & gas1.20 GWConstruction2026
7Koudiet Eddraouch power plantEl TarfOil & gas1.20 GWOperating2013
8Terga power plantAïn TémouchentOil & gas1.20 GWOperating2012
9Naama power stationNaamaOil & gas1.16 GWOperating2021
10PW Mobile power plantAdrarOil & gas1.05 GWOperating2011

Pipeline: capacity under construction

Gas & oil power plants in Algeria

See all 59 →
#NameTypeCapacityStatusStart
1Ras Djinet power plantBoumerdèsOil & gas1.87 GWOperating1986
2Oumache power stationBiskraOil & gas1.46 GWOperating2016
3Bellara power stationJijelOil & gas1.40 GWOperating2022
4Kais power stationKhenchelaOil & gas1.27 GWOperating2019
5Hadjret En Nouss power plantTipazaOil & gas1.23 GWOperating2009

Hydropower plants in Algeria

See all 3 →
#NameTypeCapacityStatusStart
1Mansouria hydroelectric plantJijelHydropower100 MWOperating1963
2Darguinah hydroelectric plantBejaiaHydropower72 MWOperating1952
3Ighil Emda hydroelectric plantBejaiaHydropower24 MWOperating1952

Wind farms in Algeria

See all 1 →
#NameTypeCapacityStatusStart
1Kabertene wind farmAdrarWind10 MWOperating2014

Solar farms in Algeria

See all 64 →
#NameTypeCapacityStatusStart
1Biskra solar farmBiskraSolar450 MWConstruction2026
2Hassi Delaa solar farmLaghouatSolar362 MWPre-construction2028
3Laghouat (Özgün İnşaat) solar farmLaghouatSolar362 MWConstruction2026
4Foulia solar farmEl OuedSolar300 MWConstruction2026
5El Oued solar farmSolar280 MWConstruction2026

Gas pipelines in Algeria

See all 46 →
#NameTypeCapacityStatusStart
1Hassi R'Mel-Arzew Gas PipelineLaghouatGas pipeline40.7 bcm/yOperating1982
2Hassi R'Mel-Arzew Gas PipelineLaghouatGas pipeline40.7 bcm/yOperating1989
3Hassi R'Mel-Arzew Gas PipelineLaghouatGas pipeline40.7 bcm/yOperating1976
4Trans-Sahara Gas PipelineGas pipeline30.0 bcm/yShelved2030
5Hassi R'Mel-Skikda Gas PipelineLaghouatGas pipeline20.5 bcm/yOperating1971

Oil & NGL pipelines in Algeria

See all 34 →
#NameTypeCapacityStatusStart
1Haoudh El Hamra-Arzew Oil PipelineOil pipeline682,795 boe/dOperating2005
2Haoudh El Hamra-Skikda Oil PipelineOil pipeline602,466 boe/dOperating1972
3Hassi Berkine-Haoudh El Hamra Oil PipelineOuarglaOil pipeline301,233 boe/dOperating2006
4Hassi Berkine-Haoudh el Hamra Oil PipelineOuarglaOil pipeline301,233 boe/dOperating1999
5Mesdar-Haoudh El Hamra Oil PipelineOuarglaOil pipeline240,986 boe/dOperating1972

LNG terminals in Algeria

See all 2 →
#NameTypeCapacityStatusStart
1Arzew-Bethioua LNG TerminalOranLNG export terminal20.8 mtpaOperating1964
2Skikda LNG TerminalSkikdaLNG export terminal4.50 mtpaOperating1972

Oil & gas fields in Algeria

See all 54 →
#NameTypeCapacityStatusStart
1Hassi Messaoud Nord Oil Field (Algeria)Oil & gas field261 million boe/yOperating
2Hassi R'Mel Oil and Gas Field (Algeria)Oil & gas field184 million boe/yOperating1961
3Hassi Messaoud Oil and Gas Field (Algeria)Oil & gas field172 million boe/yOperating1958
4Hassi Berkine Oil and Gas Field (Algeria)Oil & gas field104 million boe/yOperating2002
5Hassi Berkine Sud Oil and Gas Field (Algeria)Oil & gas field91.4 million boe/yOperating1998

Frequently asked questions

How much power generation capacity does Algeria have?

Global Energy Monitor tracks 28.4 GW of operating power plant capacity in Algeria, counting plants of all technologies above the trackers' size thresholds.

What is the largest power plant in Algeria?

The largest power plant in Algeria in the dataset is Ras Djinet power plant, a 1.87 GW oil & gas plant.

What share of Algeria's power capacity is renewable?

Renewables — hydropower, wind, solar, geothermal and bioenergy — make up about 2.3% of operating power capacity in Algeria. Note that shares of capacity differ from shares of electricity generated, because technologies run for different numbers of hours.

Does Algeria have nuclear power plants?

No operating nuclear power plant is recorded in Algeria in the dataset.

Does Algeria have LNG terminals?

Yes. The dataset lists 2 LNG terminal projects in Algeria. Operating export capacity: 25.3 mtpa.

Energy news from Algeria

Special projects