Overview
Global Energy Monitor tracks 6 units or phases at this site (under construction 1.04 GW).
Technology: gas turbine; fuel: natural gas.
Ownership: General Electricity Company of Libya.
6 further units or phases are scheduled to come online in 2026.
Why it matters
- The 7th-largest oil- and gas-fired power station in Libya by capacity (of 27 operating, under-construction and planned oil & gas facilities tracked).
- If completed, it would add 1.04 GW to Libya's oil & gas fleet — equivalent to 7% of today's operating oil & gas capacity.
Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.
Oil & gas power in Libya
Libya has 14.8 GW of operating oil & gas capacity across 23 plants in the Global Energy Monitor dataset — 97% of the country's total operating power capacity of 15.3 GW.
The oil & gas pipeline in Libya includes 3.72 GW under construction and 1.00 GW at earlier planning stages.
Other major oil & gas plants in Libya include North Benghazi power station (1.74 GW), Al Khums power station (1.61 GW) and Al Zawiya power station (1.54 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| 1 | 174 MW | Construction | gas turbine | 2026 | |
| 2 | 174 MW | Construction | gas turbine | 2026 | |
| 3 | 174 MW | Construction | gas turbine | 2026 | |
| 4 | 174 MW | Construction | gas turbine | 2026 | |
| 5 | 174 MW | Construction | gas turbine | 2026 | |
| 6 | 174 MW | Construction | gas turbine | 2026 |
How gas & oil power plants work
Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.
Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.
Technology at Zliten power plant
Open-cycle gas turbines can start within minutes and are mainly used as peaking plants, at efficiencies of roughly 30–40%.
Location
Zliten power plant is located in Al-Margab, Libya, at approximately 32.4639, 14.5725. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Zliten power plant is owned by General Electricity Company of Libya. Across the dataset, General Electricity Company of Libya is linked to 29 power plants with 14.8 GW of operating capacity.
Frequently asked questions
What is the capacity of Zliten power plant?
Zliten power plant has a capacity of 1.04 GW according to the latest Global Energy Monitor data. This figure covers the 6 units or phases listed for the site.
What type of facility is Zliten power plant?
Zliten power plant is a oil- and gas-fired power station. Open-cycle gas turbines can start within minutes and are mainly used as peaking plants, at efficiencies of roughly 30–40%.
Who owns Zliten power plant?
Zliten power plant is owned by General Electricity Company of Libya.
Where is Zliten power plant located?
It is located in Al-Margab, Libya. Approximate coordinates: 32.4639, 14.5725.
Is Zliten power plant operational?
According to the latest data, Zliten power plant is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.
When is Zliten power plant expected to start?
Start year: 2026. Current status: Construction. 6 further units or phases are scheduled to come online in 2026.
How big is Zliten power plant compared with other facilities in Libya?
Zliten power plant ranks #7 by capacity among 27 comparable oil & gas facilities tracked in Libya.