Coal · China

Tieling power station

Tieling power station is a 2.40 GW coal-fired power station located in Liaoning, China. The facility is currently in operation, with its first unit entering service in 1993.

2.40 GWCapacity
OperatingStatus
1993Start year
View on the interactive map →

Overview

Global Energy Monitor tracks 8 units or phases at this site (operating 2.40 GW, planned 1.32 GW).

Technology: subcritical, ultra-supercritical, unknown; fuel: coal: bituminous.

Ownership: Liaoning Huadian Tieling Power Generation Co Ltd (parent company: Shenyang Jinshan Energy Co Ltd).

Its 6 operating units were commissioned between 1993 and 2008.

Why it matters

  • At a typical capacity factor of 50% for this technology, it would generate roughly 11 TWh of electricity a year (indicative estimate).

Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.

Coal power in China

China has 1,259.6 GW of operating coal capacity across 1,188 plants in the Global Energy Monitor dataset — 41% of the country's total operating power capacity of 3,086.2 GW.

The coal pipeline in China includes 93.1 GW under construction and 145.8 GW at earlier planning stages.

Other major coal plants in China include Beilun power station (7.10 GW), Pingwei power station (6.54 GW) and Togtoh power station (6.12 GW).

See the full list: Coal power plants in China →

Units and phases

Unit / phaseCapacityStatusTechnologyStartRetired
Phase I Unit 1 300 MW Operating subcritical 1993
Phase I Unit 2 300 MW Operating subcritical 1993
Phase I Unit 3 300 MW Operating subcritical 1996
Phase I Unit 4 300 MW Operating subcritical 1997
Phase II Unit 5 600 MW Operating ultra-supercritical 2008
Phase II Unit 6 600 MW Operating ultra-supercritical 2008
Phase III Unit 7 660 MW Announced unknown
Phase III Unit 8 660 MW Announced unknown

How coal power plants work

A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.

Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.

Technology at Tieling power station

Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.

Location

Imagery © Esri, Maxar, Earthstar Geographics

Tieling power station is located in Liaoning, China, at approximately 42.3450, 123.8030. Open the interactive map to explore nearby power plants, high-voltage lines and substations.

Ownership

Tieling power station is owned by Liaoning Huadian Tieling Power Generation Co Ltd. The ultimate parent company is Shenyang Jinshan Energy Co Ltd. Across the dataset, Shenyang Jinshan Energy Co Ltd is linked to 8 power plants with 3.86 GW of operating capacity.

Frequently asked questions

What is the capacity of Tieling power station?

Tieling power station has a capacity of 2.40 GW according to the latest Global Energy Monitor data. This figure covers the 8 units or phases listed for the site.

What type of facility is Tieling power station?

Tieling power station is a coal-fired power station. Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.

Who owns Tieling power station?

Tieling power station is owned by Liaoning Huadian Tieling Power Generation Co Ltd. The ultimate parent company is Shenyang Jinshan Energy Co Ltd.

Where is Tieling power station located?

It is located in Liaoning, China. Approximate coordinates: 42.3450, 123.8030.

Is Tieling power station operational?

According to the latest data, Tieling power station is in operation. Operating means the facility is built and in commercial service.

When did Tieling power station start operating?

Start year: 1993. Current status: Operating. Its 6 operating units were commissioned between 1993 and 2008.

How much electricity does Tieling power station generate?

Actual output data are not published for every plant. As an indicative estimate, Tieling power station would produce about 11 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.

How big is Tieling power station compared with other facilities in China?

Tieling power station ranks #125 by capacity among 1188 comparable coal facilities tracked in China.

Nearby energy infrastructure

Sources and methodology

Source: Global Energy Monitor, Global Integrated Power Tracker, 2026-09 release. Full project profile on GEM.wiki. Last updated: 8 October 2026.

Capacity, status, ownership and unit details come from Global Energy Monitor's public trackers, which are compiled from company reports, government filings and news coverage and updated several times a year. Rankings and shares are calculated by The Daily Energy from the same dataset. Estimated annual generation uses typical capacity factors for each technology and is indicative only.

Data: Global Energy Monitor (GIPT 2026-09, GGIT 2025-11, GOIT 2026-06, GOGET 2026-03, GCMT 2026-08, OSM 2026-10) licensed under CC BY 4.0; transmission grid © OpenStreetMap contributors (ODbL). Compiled and published by The Daily Energy.