Overview
Global Energy Monitor tracks 4 units or phases at this site (under construction 1.40 GW, planned 1.40 GW).
Technology: combined cycle; fuel: natural gas.
Ownership: Sichuan Energy Investment Anju Gas Power Generation Co Ltd.
2 further units or phases are scheduled to come online in 2026.
Why it matters
- The 2nd-largest oil- and gas-fired power station in China by capacity (of 448 operating, under-construction and planned oil & gas facilities tracked).
- If completed, it would add 2.80 GW to China's oil & gas fleet — equivalent to 1.4% of today's operating oil & gas capacity.
Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.
Oil & gas power in China
China has 193.9 GW of operating oil & gas capacity across 361 plants in the Global Energy Monitor dataset — 6.3% of the country's total operating power capacity of 3,086.2 GW.
The oil & gas pipeline in China includes 24.6 GW under construction and 64.9 GW at earlier planning stages.
Other major oil & gas plants in China include Yudean Huizhou Gas power station (2.55 GW), Dongguan Ningzhou Gas power station (2.48 GW) and Huaneng Chongqing Liangjiang Gas power station (2.42 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| 1-1 | 700 MW | Construction | combined cycle | 2026 | |
| 1-2 | 700 MW | Construction | combined cycle | 2026 | |
| 2-1 | 700 MW | Announced | combined cycle | ||
| 2-2 | 700 MW | Announced | combined cycle |
How gas & oil power plants work
Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.
Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.
Technology at Sichuan Suining Anju Natural Gas power station
Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Location
Sichuan Suining Anju Natural Gas power station is located in Sichuan, China, at approximately 30.3267, 105.4866. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Sichuan Suining Anju Natural Gas power station is owned by Sichuan Energy Investment Anju Gas Power Generation Co Ltd.
Frequently asked questions
What is the capacity of Sichuan Suining Anju Natural Gas power station?
Sichuan Suining Anju Natural Gas power station has a capacity of 2.80 GW according to the latest Global Energy Monitor data. This figure covers the 4 units or phases listed for the site.
What type of facility is Sichuan Suining Anju Natural Gas power station?
Sichuan Suining Anju Natural Gas power station is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Who owns Sichuan Suining Anju Natural Gas power station?
Sichuan Suining Anju Natural Gas power station is owned by Sichuan Energy Investment Anju Gas Power Generation Co Ltd.
Where is Sichuan Suining Anju Natural Gas power station located?
It is located in Sichuan, China. Approximate coordinates: 30.3267, 105.4866.
Is Sichuan Suining Anju Natural Gas power station operational?
According to the latest data, Sichuan Suining Anju Natural Gas power station is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.
When is Sichuan Suining Anju Natural Gas power station expected to start?
Start year: 2026. Current status: Construction. 2 further units or phases are scheduled to come online in 2026.
How big is Sichuan Suining Anju Natural Gas power station compared with other facilities in China?
Sichuan Suining Anju Natural Gas power station ranks #2 by capacity among 448 comparable oil & gas facilities tracked in China.