Overview
Global Energy Monitor tracks 5 units or phases at this site (under construction 1.05 GW, planned 1.60 GW).
Technology: subcritical, ultra-supercritical, unknown; fuel: coal: subbituminous, coal: unknown.
Ownership: Jindal Steel Ltd.
2 further units or phases are scheduled to come online in 2026.
Why it matters
- The 21st-largest coal-fired power station in India by capacity (of 318 operating, under-construction and planned coal facilities tracked).
- If completed, it would add 2.65 GW to India's coal fleet — equivalent to 1% of today's operating coal capacity.
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in India
India has 253.8 GW of operating coal capacity across 285 plants in the Global Energy Monitor dataset — 52% of the country's total operating power capacity of 485.3 GW.
The coal pipeline in India includes 20.4 GW under construction and 35.6 GW at earlier planning stages.
Other major coal plants in India include Vindhyachal power station (4.76 GW), Mundra Thermal Power Project (Adani) (4.62 GW) and Ramagundam power station (4.20 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Unit 1 | 525 MW | Construction | subcritical | 2026 | |
| Unit 2 | 525 MW | Construction | subcritical | 2026 | |
| Unit 3 | 800 MW | Announced | ultra-supercritical | ||
| Unit 3 (old) | 660 MW | Cancelled | unknown | ||
| Unit 4 | 800 MW | Announced | ultra-supercritical |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Malibrahmani power station
Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Location
Malibrahmani power station is located in Odisha, India, at approximately 20.9223, 84.9911. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Malibrahmani power station is owned by Jindal Steel Ltd. Across the dataset, Jindal Steel Ltd is linked to 6 power plants in 2 countries, with 4.99 GW of operating capacity.
Frequently asked questions
What is the capacity of Malibrahmani power station?
Malibrahmani power station has a capacity of 2.65 GW according to the latest Global Energy Monitor data. This figure covers the 5 units or phases listed for the site.
What type of facility is Malibrahmani power station?
Malibrahmani power station is a coal-fired power station. Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.
Who owns Malibrahmani power station?
Malibrahmani power station is owned by Jindal Steel Ltd.
Where is Malibrahmani power station located?
It is located in Odisha, India. Approximate coordinates: 20.9223, 84.9911.
Is Malibrahmani power station operational?
According to the latest data, Malibrahmani power station is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.
When is Malibrahmani power station expected to start?
Start year: 2026. Current status: Construction. 2 further units or phases are scheduled to come online in 2026.
How big is Malibrahmani power station compared with other facilities in India?
Malibrahmani power station ranks #21 by capacity among 318 comparable coal facilities tracked in India.