Overview
Global Energy Monitor tracks 16 units or phases at this site (operating 1.20 GW, planned 1.08 GW).
Technology: subcritical, unknown; fuel: coal: subbituminous, coal: unknown.
Ownership: National Aluminium Co Ltd.
Its 10 operating units were commissioned between 1985 and 2010.
Why it matters
- At a typical capacity factor of 50% for this technology, it would generate roughly 5.3 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in India
India has 253.8 GW of operating coal capacity across 285 plants in the Global Energy Monitor dataset — 52% of the country's total operating power capacity of 485.3 GW.
The coal pipeline in India includes 20.4 GW under construction and 35.6 GW at earlier planning stages.
Other major coal plants in India include Vindhyachal power station (4.76 GW), Mundra Thermal Power Project (Adani) (4.62 GW) and Ramagundam power station (4.20 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Unit 1 | 120 MW | subcritical | 1985 | ||
| Unit 2 | 120 MW | subcritical | 1985 | ||
| Unit 3 | 120 MW | subcritical | 1985 | ||
| Unit 4 | 120 MW | subcritical | 1985 | ||
| Unit 5 | 120 MW | subcritical | 1990 | ||
| Unit 6 | 120 MW | subcritical | 1994 | ||
| Unit 7 | 120 MW | subcritical | 2002 | ||
| Unit 8 | 120 MW | subcritical | 2009 | ||
| Unit 9 | 120 MW | subcritical | 2010 | ||
| Unit 10 | 120 MW | subcritical | 2010 | ||
| Unit 11 | 270 MW | Pre-construction | subcritical | ||
| Unit 11 (old) | 250 MW | Cancelled | subcritical | ||
| Unit 12 | 270 MW | Pre-construction | subcritical | ||
| Unit 12 (old) | 250 MW | Cancelled | unknown | ||
| Unit 13 | 270 MW | Pre-construction | subcritical | ||
| Unit 14 | 270 MW | Pre-construction | subcritical |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Angul Smelter power station
Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Location
Angul Smelter power station is located in Odisha, India, at approximately 20.8490, 85.1902. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Angul Smelter power station is owned by National Aluminium Co Ltd. Across the dataset, National Aluminium Co Ltd is linked to 3 power plants with 1.44 GW of operating capacity.
Frequently asked questions
What is the capacity of Angul Smelter power station?
Angul Smelter power station has a capacity of 1.20 GW according to the latest Global Energy Monitor data. This figure covers the 16 units or phases listed for the site.
What type of facility is Angul Smelter power station?
Angul Smelter power station is a coal-fired power station. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Who owns Angul Smelter power station?
Angul Smelter power station is owned by National Aluminium Co Ltd.
Where is Angul Smelter power station located?
It is located in Odisha, India. Approximate coordinates: 20.8490, 85.1902.
Is Angul Smelter power station operational?
According to the latest data, Angul Smelter power station is in operation. Operating means the facility is built and in commercial service.
When did Angul Smelter power station start operating?
Start year: 1985. Current status: Operating. Its 10 operating units were commissioned between 1985 and 2010.
How much electricity does Angul Smelter power station generate?
Actual output data are not published for every plant. As an indicative estimate, Angul Smelter power station would produce about 5.3 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Angul Smelter power station compared with other facilities in India?
Angul Smelter power station ranks #84 by capacity among 285 comparable coal facilities tracked in India.