Overview
Global Energy Monitor tracks 4 units or phases at this site (under construction 4.00 GW).
Technology: ultra-supercritical; fuel: coal: unknown.
Ownership: Huadian (Inner Mongolia) New Energy Co Ltd (parent company: China Huadian Corp Ltd; Huadian Power International Co Ltd; unknown).
4 further units or phases are scheduled to come online in 2025–2026.
Why it matters
- Ranks #52 worldwide among coal facilities of the same status group by capacity.
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in China
China has 1,259.6 GW of operating coal capacity across 1,188 plants in the Global Energy Monitor dataset — 41% of the country's total operating power capacity of 3,086.2 GW.
The coal pipeline in China includes 93.1 GW under construction and 145.8 GW at earlier planning stages.
Other major coal plants in China include Beilun power station (7.10 GW), Pingwei power station (6.54 GW) and Togtoh power station (6.12 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Unit 1 | 1.00 GW | Construction | ultra-supercritical | 2025 | |
| Unit 2 | 1.00 GW | Construction | ultra-supercritical | 2026 | |
| Unit 3 | 1.00 GW | Construction | ultra-supercritical | 2026 | |
| Unit 4 | 1.00 GW | Construction | ultra-supercritical | 2026 |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Huadian Tengger power station
Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.
Location
Huadian Tengger power station is located in Inner Mongolia, China, at approximately 40.6421, 106.2655. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Huadian Tengger power station is owned by Huadian (Inner Mongolia) New Energy Co Ltd. The ultimate parent company is China Huadian Corp Ltd; Huadian Power International Co Ltd; unknown. Across the dataset, China Huadian Corp Ltd is linked to 156 power plants in 4 countries, with 78.5 GW of operating capacity.
Frequently asked questions
What is the capacity of Huadian Tengger power station?
Huadian Tengger power station has a capacity of 4.00 GW according to the latest Global Energy Monitor data. This figure covers the 4 units or phases listed for the site.
What type of facility is Huadian Tengger power station?
Huadian Tengger power station is a coal-fired power station. Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.
Who owns Huadian Tengger power station?
Huadian Tengger power station is owned by Huadian (Inner Mongolia) New Energy Co Ltd. The ultimate parent company is China Huadian Corp Ltd; Huadian Power International Co Ltd; unknown.
Where is Huadian Tengger power station located?
It is located in Inner Mongolia, China. Approximate coordinates: 40.6421, 106.2655.
Is Huadian Tengger power station operational?
According to the latest data, Huadian Tengger power station is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.
When is Huadian Tengger power station expected to start?
Start year: 2025. Current status: Construction. 4 further units or phases are scheduled to come online in 2025–2026.
How big is Huadian Tengger power station compared with other facilities in China?
Huadian Tengger power station ranks #31 by capacity among 1380 comparable coal facilities tracked in China.
Nearby energy infrastructure
- Inner Mongolia Dengkou Ecological Management solar farm
- Inner Mongolia Northeast Wulanbuhe Desert Megabase solar farm
- Inner Mongolia Bayannaoer Solar/Storage/Ecological Management complex
- Inner Mongolia Urad Rear Banner (Mengneng) Guaranteed Off-Take wind-storage farm
- Taiyanggou hydroelectric plant
- Inner Mongolia Alxa League Renewable Power to Wuhai solar farm
- Wuhai hydroelectric plant
- Inner Mongolia Alxa High-Tech Development Zone solar farm