Coal · China

Huadian Tengger power station

Huadian Tengger power station is a 4.00 GW coal-fired power station located in Inner Mongolia, China. The facility is currently under construction, with a targeted start date of 2025.

4.00 GWCapacity (all phases)
ConstructionStatus
2025Start year
View on the interactive map →

Overview

Global Energy Monitor tracks 4 units or phases at this site (under construction 4.00 GW).

Technology: ultra-supercritical; fuel: coal: unknown.

Ownership: Huadian (Inner Mongolia) New Energy Co Ltd (parent company: China Huadian Corp Ltd; Huadian Power International Co Ltd; unknown).

4 further units or phases are scheduled to come online in 2025–2026.

Why it matters

  • Ranks #52 worldwide among coal facilities of the same status group by capacity.

Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.

Coal power in China

China has 1,259.6 GW of operating coal capacity across 1,188 plants in the Global Energy Monitor dataset — 41% of the country's total operating power capacity of 3,086.2 GW.

The coal pipeline in China includes 93.1 GW under construction and 145.8 GW at earlier planning stages.

Other major coal plants in China include Beilun power station (7.10 GW), Pingwei power station (6.54 GW) and Togtoh power station (6.12 GW).

See the full list: Coal power plants in China →

Units and phases

Unit / phaseCapacityStatusTechnologyStartRetired
Unit 1 1.00 GW Construction ultra-supercritical 2025
Unit 2 1.00 GW Construction ultra-supercritical 2026
Unit 3 1.00 GW Construction ultra-supercritical 2026
Unit 4 1.00 GW Construction ultra-supercritical 2026

How coal power plants work

A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.

Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.

Technology at Huadian Tengger power station

Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.

Location

Location is approximate. Imagery © Esri, Maxar, Earthstar Geographics

Huadian Tengger power station is located in Inner Mongolia, China, at approximately 40.6421, 106.2655. Open the interactive map to explore nearby power plants, high-voltage lines and substations.

Ownership

Huadian Tengger power station is owned by Huadian (Inner Mongolia) New Energy Co Ltd. The ultimate parent company is China Huadian Corp Ltd; Huadian Power International Co Ltd; unknown. Across the dataset, China Huadian Corp Ltd is linked to 156 power plants in 4 countries, with 78.5 GW of operating capacity.

Frequently asked questions

What is the capacity of Huadian Tengger power station?

Huadian Tengger power station has a capacity of 4.00 GW according to the latest Global Energy Monitor data. This figure covers the 4 units or phases listed for the site.

What type of facility is Huadian Tengger power station?

Huadian Tengger power station is a coal-fired power station. Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.

Who owns Huadian Tengger power station?

Huadian Tengger power station is owned by Huadian (Inner Mongolia) New Energy Co Ltd. The ultimate parent company is China Huadian Corp Ltd; Huadian Power International Co Ltd; unknown.

Where is Huadian Tengger power station located?

It is located in Inner Mongolia, China. Approximate coordinates: 40.6421, 106.2655.

Is Huadian Tengger power station operational?

According to the latest data, Huadian Tengger power station is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.

When is Huadian Tengger power station expected to start?

Start year: 2025. Current status: Construction. 4 further units or phases are scheduled to come online in 2025–2026.

How big is Huadian Tengger power station compared with other facilities in China?

Huadian Tengger power station ranks #31 by capacity among 1380 comparable coal facilities tracked in China.

Nearby energy infrastructure

Other assets of the same owner

Sources and methodology

Source: Global Energy Monitor, Global Integrated Power Tracker, 2026-09 release. Full project profile on GEM.wiki. Last updated: 8 October 2026.

Capacity, status, ownership and unit details come from Global Energy Monitor's public trackers, which are compiled from company reports, government filings and news coverage and updated several times a year. Rankings and shares are calculated by The Daily Energy from the same dataset. Estimated annual generation uses typical capacity factors for each technology and is indicative only.

Data: Global Energy Monitor (GIPT 2026-09, GGIT 2025-11, GOIT 2026-06, GOGET 2026-03, GCMT 2026-08, OSM 2026-10) licensed under CC BY 4.0; transmission grid © OpenStreetMap contributors (ODbL). Compiled and published by The Daily Energy.

Special projects