Overview
Global Energy Monitor tracks 6 units or phases at this site (operating 1.07 GW, under construction 675 MW, retired 220 MW).
Technology: subcritical, combined cycle; fuel: coal: bituminous, natural gas.
Ownership: EnBW Energie Baden-Württemberg AG.
Its 3 operating units were commissioned between 1965 and 1985. 1 further units or phases are scheduled to come online in 2027. 2 units have already been retired (2015). 3 operating units have a planned retirement date, the earliest in 2026.
Why it matters
- The 11th-largest coal-fired power station in Germany by capacity (of 38 operating coal facilities tracked).
- Provides about 4.1% of Germany's operating coal capacity and roughly 0.7% of all operating power capacity in the country in the dataset.
- At a typical capacity factor of 50% for this technology, it would generate roughly 4.7 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in Germany
Germany has 25.9 GW of operating coal capacity across 38 plants in the Global Energy Monitor dataset — 16% of the country's total operating power capacity of 161.9 GW.
Other major coal plants in Germany include Boxberg power station (2.58 GW), Niederaussem power station (2.28 GW) and Neurath power station (2.20 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Unit 3 | 110 MW | Retired | subcritical | 1958 | 2015 |
| Unit 4 | 110 MW | Retired | subcritical | 1960 | 2015 |
| Unit 5 | 125 MW | subcritical | 1965 | 2026 | |
| Unit 6 | 125 MW | subcritical | 1966 | 2026 | |
| Unit 7 | 816 MW | subcritical | 1985 | 2026 | |
| Unit A, timepoint 1 | 675 MW | Construction | combined cycle | 2027 |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Heilbronn power station
Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Location
Heilbronn power station is located in Baden-Württemberg, Germany, at approximately 49.1753, 9.2074. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Heilbronn power station is owned by EnBW Energie Baden-Württemberg AG. Across the dataset, EnBW Energie Baden-Württemberg AG is linked to 99 power plants in 5 countries, with 14.8 GW of operating capacity.
Frequently asked questions
What is the capacity of Heilbronn power station?
Heilbronn power station has a capacity of 1.07 GW according to the latest Global Energy Monitor data. This figure covers the 6 units or phases listed for the site.
What type of facility is Heilbronn power station?
Heilbronn power station is a coal-fired power station. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Who owns Heilbronn power station?
Heilbronn power station is owned by EnBW Energie Baden-Württemberg AG.
Where is Heilbronn power station located?
It is located in Baden-Württemberg, Germany. Approximate coordinates: 49.1753, 9.2074.
Is Heilbronn power station operational?
According to the latest data, Heilbronn power station is in operation. Operating means the facility is built and in commercial service.
When did Heilbronn power station start operating?
Start year: 1965. Current status: Operating. Its 3 operating units were commissioned between 1965 and 1985. 1 further units or phases are scheduled to come online in 2027. 2 units have already been retired (2015). 3 operating units have a planned retirement date, the earliest in 2026.
How much electricity does Heilbronn power station generate?
Actual output data are not published for every plant. As an indicative estimate, Heilbronn power station would produce about 4.7 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Heilbronn power station compared with other facilities in Germany?
Heilbronn power station ranks #11 by capacity among 38 comparable coal facilities tracked in Germany.