Overview
Global Energy Monitor tracks 8 units or phases at this site (operating 1.80 GW, retired 440 MW).
Technology: subcritical, supercritical; fuel: coal: bituminous.
Ownership: Hebi Fenghe Power Generating Co Ltd (parent company: Henan Yuneng Holdings Co Ltd; Henan Province Energy Chemical Group Co Ltd; Shenzhen Yingshui Investment Group Co Ltd; unknown).
Its 4 operating units were commissioned between 2003 and 2007. 2 units have already been retired (2010).
Why it matters
- At a typical capacity factor of 50% for this technology, it would generate roughly 7.9 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in China
China has 1,259.6 GW of operating coal capacity across 1,188 plants in the Global Energy Monitor dataset — 41% of the country's total operating power capacity of 3,086.2 GW.
The coal pipeline in China includes 93.1 GW under construction and 145.8 GW at earlier planning stages.
Other major coal plants in China include Beilun power station (7.10 GW), Pingwei power station (6.54 GW) and Togtoh power station (6.12 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Phase I Unit 1 | 220 MW | Retired | subcritical | 1991 | 2010 |
| Phase I Unit 2 | 220 MW | Retired | subcritical | 1992 | 2010 |
| Phase II Unit 1 | 300 MW | subcritical | 2003 | 2021 | |
| Phase II Unit 2 | 300 MW | subcritical | 2003 | ||
| Phase III Unit 1 | 600 MW | supercritical | 2007 | ||
| Phase III Unit 2 | 600 MW | supercritical | 2007 | ||
| Phase III Unit 3 | 1.00 GW | Cancelled | supercritical | ||
| Phase III Unit 4 | 1.00 GW | Cancelled | supercritical |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Hebi power station
Supercritical units operate above the critical pressure of water, reaching efficiencies of roughly 38–42% and lower emissions per megawatt-hour than subcritical units. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Location
Hebi power station is located in Henan, China, at approximately 35.8514, 114.1798. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Hebi power station is owned by Hebi Fenghe Power Generating Co Ltd. The ultimate parent company is Henan Yuneng Holdings Co Ltd; Henan Province Energy Chemical Group Co Ltd; Shenzhen Yingshui Investment Group Co Ltd; unknown. Across the dataset, Henan Yuneng Holdings Co Ltd is linked to 13 power plants with 10.9 GW of operating capacity.
Frequently asked questions
What is the capacity of Hebi power station?
Hebi power station has a capacity of 1.80 GW according to the latest Global Energy Monitor data. This figure covers the 8 units or phases listed for the site.
What type of facility is Hebi power station?
Hebi power station is a coal-fired power station. Supercritical units operate above the critical pressure of water, reaching efficiencies of roughly 38–42% and lower emissions per megawatt-hour than subcritical units.
Who owns Hebi power station?
Hebi power station is owned by Hebi Fenghe Power Generating Co Ltd. The ultimate parent company is Henan Yuneng Holdings Co Ltd; Henan Province Energy Chemical Group Co Ltd; Shenzhen Yingshui Investment Group Co Ltd; unknown.
Where is Hebi power station located?
It is located in Henan, China. Approximate coordinates: 35.8514, 114.1798.
Is Hebi power station operational?
According to the latest data, Hebi power station is in operation. Operating means the facility is built and in commercial service.
When did Hebi power station start operating?
Start year: 2003. Current status: Operating. Its 4 operating units were commissioned between 2003 and 2007. 2 units have already been retired (2010).
How much electricity does Hebi power station generate?
Actual output data are not published for every plant. As an indicative estimate, Hebi power station would produce about 7.9 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Hebi power station compared with other facilities in China?
Hebi power station ranks #218 by capacity among 1188 comparable coal facilities tracked in China.