Overview
Global Energy Monitor tracks 2 units or phases at this site (under construction 560 MW, planned 560 MW).
Technology: combined cycle; fuel: natural gas, other: hydrogen (green) [0%], natural gas.
Ownership: Energa SA.
2 further units or phases are scheduled to come online in 2026–2029.
Why it matters
- The 3rd-largest oil- and gas-fired power station in Poland by capacity (of 34 operating, under-construction and planned oil & gas facilities tracked).
- If completed, it would add 1.12 GW to Poland's oil & gas fleet — equivalent to 12% of today's operating oil & gas capacity.
Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.
Oil & gas power in Poland
Poland has 9.28 GW of operating oil & gas capacity across 26 plants in the Global Energy Monitor dataset — 17% of the country's total operating power capacity of 53.3 GW.
The oil & gas pipeline in Poland includes 2.28 GW under construction and 1.66 GW at earlier planning stages.
Other major oil & gas plants in Poland include Polaniec power station (1.88 GW), Dolna Odra power station (1.83 GW) and Zeran power station (1.08 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| CC1, timepoint 1 | 560 MW | Construction | combined cycle | 2026 | |
| CC2 | 560 MW | Pre-construction | combined cycle | 2029 |
How gas & oil power plants work
Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.
Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.
Technology at Grudziądz power station
Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Location
Grudziądz power station is located in Kujawsko-Pomorskie, Poland, at approximately 53.4838, 18.7536. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Grudziądz power station is owned by Energa SA. Across the dataset, Energa SA is linked to 3 power plants with 681 MW of operating capacity.
Frequently asked questions
What is the capacity of Grudziądz power station?
Grudziądz power station has a capacity of 1.12 GW according to the latest Global Energy Monitor data. This figure covers the 2 units or phases listed for the site.
What type of facility is Grudziądz power station?
Grudziądz power station is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Who owns Grudziądz power station?
Grudziądz power station is owned by Energa SA.
Where is Grudziądz power station located?
It is located in Kujawsko-Pomorskie, Poland. Approximate coordinates: 53.4838, 18.7536.
Is Grudziądz power station operational?
According to the latest data, Grudziądz power station is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.
When is Grudziądz power station expected to start?
Start year: 2026. Current status: Construction. 2 further units or phases are scheduled to come online in 2026–2029.
How big is Grudziądz power station compared with other facilities in Poland?
Grudziądz power station ranks #3 by capacity among 34 comparable oil & gas facilities tracked in Poland.