Overview
Global Energy Monitor tracks 13 units or phases at this site (operating 1.29 GW, retired 568 MW).
Technology: gas turbine, subcritical, steam turbine; fuel: fuel oil, fossil gas: natural gas, coal: bituminous, natural gas.
Ownership: Alabama Power Co (parent company: Southern Co).
Its 11 operating units were commissioned between 1995 and 2016. 2 units have already been retired (2016).
Why it matters
- At a typical capacity factor of 50% for this technology, it would generate roughly 5.6 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in United States
United States has 167.4 GW of operating coal capacity across 181 plants in the Global Energy Monitor dataset — 13% of the country's total operating power capacity of 1,280.9 GW.
The coal pipeline in United States includes 6.24 GW under construction and 6.81 GW at earlier planning stages.
Other major coal plants in United States include Homer City Generating Station (4.71 GW), Parish Generating Station (3.95 GW) and Plant Bowen (3.50 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| GT2 | 80 MW | gas turbine | 1996 | ||
| GT3 | 80 MW | gas turbine | 1995 | ||
| GT4 | 80 MW | gas turbine | 1995 | ||
| GT5 | 80 MW | gas turbine | 1995 | ||
| GT6 | 80 MW | gas turbine | 1995 | ||
| GT7 | 80 MW | gas turbine | 1995 | ||
| GT8 | 80 MW | gas turbine | 1996 | ||
| GT9 | 80 MW | gas turbine | 1996 | ||
| GT10 | 80 MW | gas turbine | 1996 | ||
| Unit 1, timepoint 1 | 299 MW | Retired | subcritical | 1965 | 2016 |
| Unit 1, timepoint 2 | 299 MW | steam turbine | 2016 | ||
| Unit 2, timepoint 1 | 269 MW | Retired | subcritical | 1966 | 2016 |
| Unit 2, timepoint 2 | 269 MW | steam turbine | 2016 |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Greene County Steam Plant
Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity. Open-cycle gas turbines can start within minutes and are mainly used as peaking plants, at efficiencies of roughly 30–40%. Steam-turbine units burn fuel in a boiler to raise steam; they are generally older and less flexible than combined-cycle plants.
Location
Greene County Steam Plant is located in Alabama, United States, at approximately 32.6013, -87.7816. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Greene County Steam Plant is owned by Alabama Power Co. The ultimate parent company is Southern Co. Across the dataset, Southern Co is linked to 43 power plants with 37.8 GW of operating capacity.
Frequently asked questions
What is the capacity of Greene County Steam Plant?
Greene County Steam Plant has a capacity of 1.29 GW according to the latest Global Energy Monitor data. This figure covers the 13 units or phases listed for the site.
What type of facility is Greene County Steam Plant?
Greene County Steam Plant is a coal-fired power station. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Who owns Greene County Steam Plant?
Greene County Steam Plant is owned by Alabama Power Co. The ultimate parent company is Southern Co.
Where is Greene County Steam Plant located?
It is located in Alabama, United States. Approximate coordinates: 32.6013, -87.7816.
Is Greene County Steam Plant operational?
According to the latest data, Greene County Steam Plant is in operation. Operating means the facility is built and in commercial service.
When did Greene County Steam Plant start operating?
Start year: 1995. Current status: Operating. Its 11 operating units were commissioned between 1995 and 2016. 2 units have already been retired (2016).
How much electricity does Greene County Steam Plant generate?
Actual output data are not published for every plant. As an indicative estimate, Greene County Steam Plant would produce about 5.6 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Greene County Steam Plant compared with other facilities in United States?
Greene County Steam Plant ranks #56 by capacity among 181 comparable coal facilities tracked in United States.