Overview
Technology: combined cycle; fuel: natural gas.
Ownership: UCC Holding Consortium (parent company: Cengiz Holding AS; Power International Holding WLL; Power International USA LLC; International Holding Company; Kalyon İnşaat Sanayi Ve Ticaret AŞ).
Why it matters
- The 5th-largest oil- and gas-fired power station in Syria by capacity (of 25 operating, under-construction and planned oil & gas facilities tracked).
- If completed, it would add 1.00 GW to Syria's oil & gas fleet — equivalent to 13% of today's operating oil & gas capacity.
Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.
Oil & gas power in Syria
Syria has 7.66 GW of operating oil & gas capacity across 15 plants in the Global Energy Monitor dataset — 81% of the country's total operating power capacity of 9.44 GW.
The oil & gas pipeline in Syria includes 3.55 GW under construction and 3.70 GW at earlier planning stages.
Other major oil & gas plants in Syria include Deir Ali power station (1.50 GW), Jandar Gas power plant (1.18 GW) and Teshreen power station (1.08 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| 1 | 1.00 GW | Construction | combined cycle | 2028 |
How gas & oil power plants work
Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.
Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.
Technology at Deir El Zor Combind Cycle power plant
Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Location
Deir El Zor Combind Cycle power plant is located in Deirez-Zor, Syria, at approximately 35.3321, 40.1242. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Deir El Zor Combind Cycle power plant is owned by UCC Holding Consortium. The ultimate parent company is Cengiz Holding AS; Power International Holding WLL; Power International USA LLC; International Holding Company; Kalyon İnşaat Sanayi Ve Ticaret AŞ. Across the dataset, Cengiz Holding AS is linked to 10 power plants in 3 countries, with 2.89 GW of operating capacity.
Frequently asked questions
What is the capacity of Deir El Zor Combind Cycle power plant?
Deir El Zor Combind Cycle power plant has a capacity of 1.00 GW according to the latest Global Energy Monitor data.
What type of facility is Deir El Zor Combind Cycle power plant?
Deir El Zor Combind Cycle power plant is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Who owns Deir El Zor Combind Cycle power plant?
Deir El Zor Combind Cycle power plant is owned by UCC Holding Consortium. The ultimate parent company is Cengiz Holding AS; Power International Holding WLL; Power International USA LLC; International Holding Company; Kalyon İnşaat Sanayi Ve Ticaret AŞ.
Where is Deir El Zor Combind Cycle power plant located?
It is located in Deirez-Zor, Syria. Approximate coordinates: 35.3321, 40.1242.
Is Deir El Zor Combind Cycle power plant operational?
According to the latest data, Deir El Zor Combind Cycle power plant is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.
When is Deir El Zor Combind Cycle power plant expected to start?
Start year: 2028. Current status: Construction.
How big is Deir El Zor Combind Cycle power plant compared with other facilities in Syria?
Deir El Zor Combind Cycle power plant ranks #5 by capacity among 25 comparable oil & gas facilities tracked in Syria.