Freeport LNG Terminal is a 34.8 mtpa LNG import (regasification) terminal in Texas, United States. It is currently in operation, with operations starting in 2008.

34.8 mtpaCapacity
OperatingStatus
2008Start year
View on the interactive map →

Overview

The tracker lists 6 trains, units or expansion phases at the terminal.

Capacity is expressed in million tonnes per annum (mtpa) of LNG that can be received and regasified.

One mtpa of LNG corresponds to roughly 1.36 billion cubic metres of natural gas per year, so this capacity equals about 47.3 bcm/y of gas.

Ownership: Freeport LNG Development LP (parent company: Freeport LNG Investments LLP; Chubu Electric Power Co Inc; Tokyo Electric Power Co; Osaka Gas Co Ltd).

Its 5 operating units were commissioned between 2008 and 2024.

Why it matters

  • The largest LNG import (regasification) terminal in United States by capacity, out of 5 operating lng import terminal facilities tracked in the country.
  • Ranks #3 worldwide among lng import terminal facilities of the same status group by capacity.

Import terminals regasify liquefied natural gas delivered by tanker and inject it into the grid, giving countries access to seaborne gas supply from many exporters.

LNG terminals in United States

The dataset tracks 39 lng terminals in United States, including operating, planned and shelved projects.

United States has 45.9 mtpa of operating LNG import capacity across 5 terminals.

United States has 258.0 mtpa of operating LNG export capacity across 8 terminals.

See the full list: LNG terminals in United States →

Trains and phases

Unit / phaseCapacityStatusTechnologyStartRetired
Import Terminal 13.2 mtpa Operating 2008
T4 5.10 mtpa Proposed
T3 5.00 mtpa Operating 2020
T2 5.00 mtpa Operating 2019
T1 5.00 mtpa Operating 2019
Debottlenecking 1.50 mtpa Operating 2024

How lng terminals work

An LNG import terminal receives liquefied natural gas from tankers, stores it at around −162 °C in insulated tanks and warms it back into gas (regasification) before sending it into the pipeline grid. Many newer terminals are floating storage and regasification units (FSRUs), which can be installed much faster than onshore plants.

Import terminals give countries access to gas from many exporters worldwide, improving supply security and price competition — a role that became especially visible in Europe after 2022.

Location

Location is approximate. Imagery © Esri, Maxar, Earthstar Geographics

Freeport LNG Terminal is located in Texas, United States, at approximately 28.9320, -95.3174. Open the interactive map to explore nearby power plants, high-voltage lines and substations.

Ownership

Freeport LNG Terminal is owned by Freeport LNG Development LP. The ultimate parent company is Freeport LNG Investments LLP; Chubu Electric Power Co Inc; Tokyo Electric Power Co; Osaka Gas Co Ltd.

Frequently asked questions

What is the capacity of Freeport LNG Terminal?

Freeport LNG Terminal has a capacity of 34.8 mtpa according to the latest Global Energy Monitor data. This figure covers the 6 units or phases listed for the site.

What type of facility is Freeport LNG Terminal?

Freeport LNG Terminal is a LNG import (regasification) terminal.

Who owns Freeport LNG Terminal?

Freeport LNG Terminal is owned by Freeport LNG Development LP. The ultimate parent company is Freeport LNG Investments LLP; Chubu Electric Power Co Inc; Tokyo Electric Power Co; Osaka Gas Co Ltd.

Where is Freeport LNG Terminal located?

It is located in Texas, United States. Approximate coordinates: 28.9320, -95.3174.

Is Freeport LNG Terminal operational?

According to the latest data, Freeport LNG Terminal is in operation. Operating means the facility is built and in commercial service.

When did Freeport LNG Terminal start operating?

Start year: 2008. Current status: Operating. Its 5 operating units were commissioned between 2008 and 2024.

How big is Freeport LNG Terminal compared with other facilities in United States?

Freeport LNG Terminal ranks #1 by capacity among 5 comparable lng import terminal facilities tracked in United States.

Latest news on Freeport LNG Terminal

Nearby energy infrastructure

Sources and methodology

Source: Global Energy Monitor, Global Gas Infrastructure Tracker, 2025-11 release. Full project profile on GEM.wiki. Last updated: 9 October 2026.

Capacity, status, ownership and unit details come from Global Energy Monitor's public trackers, which are compiled from company reports, government filings and news coverage and updated several times a year. Rankings and shares are calculated by The Daily Energy from the same dataset. Estimated annual generation uses typical capacity factors for each technology and is indicative only.

Data: Global Energy Monitor (GIPT 2026-09, GGIT 2025-11, GOIT 2026-06, GOGET 2026-03, GCMT 2026-08, OSM 2026-10) licensed under CC BY 4.0; transmission grid © OpenStreetMap contributors (ODbL). Compiled and published by The Daily Energy.