Overview
Global Energy Monitor tracks 5 units or phases at this site (operating 1.86 GW).
Technology: subcritical, ultra-supercritical; fuel: coal: bituminous.
Ownership: Xiamen Huaxiapower International Development Co Ltd (parent company: SDIC Power Holdings Co Ltd; Fujian Province Investment Development Group Co Ltd; Xiamen Jin Yuan Investment Group Co Ltd).
Its 5 operating units were commissioned between 1996 and 2025.
Why it matters
- At a typical capacity factor of 50% for this technology, it would generate roughly 8.1 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in China
China has 1,259.6 GW of operating coal capacity across 1,188 plants in the Global Energy Monitor dataset — 41% of the country's total operating power capacity of 3,086.2 GW.
The coal pipeline in China includes 93.1 GW under construction and 145.8 GW at earlier planning stages.
Other major coal plants in China include Beilun power station (7.10 GW), Pingwei power station (6.54 GW) and Togtoh power station (6.12 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Unit 1 | 300 MW | subcritical | 1996 | 2025 | |
| Unit 2 | 300 MW | subcritical | 1996 | 2025 | |
| Unit 3 | 300 MW | subcritical | 2006 | ||
| Unit 4 | 300 MW | subcritical | 2006 | ||
| Unit 5 | 660 MW | ultra-supercritical | 2025 |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Xiamen Songyu power station
Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Location
Xiamen Songyu power station is located in Fujian, China, at approximately 24.4461, 118.0268. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Xiamen Songyu power station is owned by Xiamen Huaxiapower International Development Co Ltd. The ultimate parent company is SDIC Power Holdings Co Ltd; Fujian Province Investment Development Group Co Ltd; Xiamen Jin Yuan Investment Group Co Ltd. Across the dataset, SDIC Power Holdings Co Ltd is linked to 52 power plants in 2 countries, with 26.6 GW of operating capacity.
Frequently asked questions
What is the capacity of Xiamen Songyu power station?
Xiamen Songyu power station has a capacity of 1.86 GW according to the latest Global Energy Monitor data. This figure covers the 5 units or phases listed for the site.
What type of facility is Xiamen Songyu power station?
Xiamen Songyu power station is a coal-fired power station. Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.
Who owns Xiamen Songyu power station?
Xiamen Songyu power station is owned by Xiamen Huaxiapower International Development Co Ltd. The ultimate parent company is SDIC Power Holdings Co Ltd; Fujian Province Investment Development Group Co Ltd; Xiamen Jin Yuan Investment Group Co Ltd.
Where is Xiamen Songyu power station located?
It is located in Fujian, China. Approximate coordinates: 24.4461, 118.0268.
Is Xiamen Songyu power station operational?
According to the latest data, Xiamen Songyu power station is in operation. Operating means the facility is built and in commercial service.
When did Xiamen Songyu power station start operating?
Start year: 1996. Current status: Operating. Its 5 operating units were commissioned between 1996 and 2025.
How much electricity does Xiamen Songyu power station generate?
Actual output data are not published for every plant. As an indicative estimate, Xiamen Songyu power station would produce about 8.1 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Xiamen Songyu power station compared with other facilities in China?
Xiamen Songyu power station ranks #212 by capacity among 1188 comparable coal facilities tracked in China.