Overview
Global Energy Monitor tracks 7 units or phases at this site (under construction 1.75 GW, retired 1.29 GW).
Technology: combined cycle, subcritical; fuel: natural gas, coal: bituminous.
Ownership: Complexul Energetic Hunedoara SA.
1 further units or phases are scheduled to come online in 2026. 6 units have already been retired (2012–2021).
Why it matters
- The largest oil- and gas-fired power station in Romania by capacity, out of 23 operating, under-construction and planned oil & gas facilities tracked in the country.
- If completed, it would add 1.75 GW to Romania's oil & gas fleet — equivalent to 41% of today's operating oil & gas capacity.
Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.
Oil & gas power in Romania
Romania has 4.25 GW of operating oil & gas capacity across 16 plants in the Global Energy Monitor dataset — 19% of the country's total operating power capacity of 22.3 GW.
The oil & gas pipeline in Romania includes 1.99 GW under construction and 628 MW at earlier planning stages.
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| CC, timepoint 1 | 1.75 GW | Construction | combined cycle | 2026 | |
| Unit 1 | 210 MW | Retired | subcritical | 1969 | 2012 |
| Unit 2 | 210 MW | Retired | subcritical | 1975 | 2021 |
| Unit 3 | 235 MW | Retired | subcritical | 1976 | 2021 |
| Unit 4 | 210 MW | Retired | subcritical | 1977 | 2021 |
| Unit 5 | 210 MW | Retired | subcritical | 1978 | 2021 |
| Unit 6 | 210 MW | Retired | subcritical | 1978 | 2021 |
How gas & oil power plants work
Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.
Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.
Technology at Mintia-Deva power station
Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Location
Mintia-Deva power station is located in Hunedoara, Romania, at approximately 45.9128, 22.8261. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Mintia-Deva power station is owned by Complexul Energetic Hunedoara SA. Across the dataset, Complexul Energetic Hunedoara SA is linked to 2 power plants with 150 MW of operating capacity.
Frequently asked questions
What is the capacity of Mintia-Deva power station?
Mintia-Deva power station has a capacity of 1.75 GW according to the latest Global Energy Monitor data. This figure covers the 7 units or phases listed for the site.
What type of facility is Mintia-Deva power station?
Mintia-Deva power station is a oil- and gas-fired power station. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Who owns Mintia-Deva power station?
Mintia-Deva power station is owned by Complexul Energetic Hunedoara SA.
Where is Mintia-Deva power station located?
It is located in Hunedoara, Romania. Approximate coordinates: 45.9128, 22.8261.
Is Mintia-Deva power station operational?
According to the latest data, Mintia-Deva power station is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.
When is Mintia-Deva power station expected to start?
Start year: 1969. Current status: Construction. 1 further units or phases are scheduled to come online in 2026. 6 units have already been retired (2012–2021).
How big is Mintia-Deva power station compared with other facilities in Romania?
Mintia-Deva power station ranks #1 by capacity among 23 comparable oil & gas facilities tracked in Romania.