Overview
Global Energy Monitor tracks 6 units or phases at this site (operating 2.00 GW, planned 4.68 GW).
Technology: pressurized water reactor.
Ownership: SE NNEGC "Energoatom".
Its 2 operating units were commissioned between 1988 and 2005. 2 further units or phases are scheduled to come online in 2032.
Why it matters
- The 4th-largest nuclear power plant in Ukraine by capacity (of 4 operating nuclear facilities tracked).
- Provides about 14% of Ukraine's operating nuclear capacity and roughly 5.9% of all operating power capacity in the country in the dataset.
- Ranks #90 worldwide among nuclear facilities of the same status group by capacity.
- At a typical capacity factor of 85% for this technology, it would generate roughly 15 TWh of electricity a year (indicative estimate).
Nuclear plants supply large volumes of low-carbon baseload electricity with very high capacity factors, so a single station can cover a significant share of national demand.
Nuclear power in Ukraine
Ukraine has 13.8 GW of operating nuclear capacity across 4 plants in the Global Energy Monitor dataset — 41% of the country's total operating power capacity of 33.7 GW.
Other major nuclear plants in Ukraine include Zaporizhzhia nuclear power plant (6.00 GW), South Ukraine nuclear power plant (3.00 GW) and Rivne nuclear power plant (2.84 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| 1 | 1.00 GW | pressurized water reactor | 1988 | ||
| 2 | 1.00 GW | pressurized water reactor | 2005 | ||
| 3 | 1.09 GW | Pre-construction | pressurized water reactor | ||
| 4 | 1.09 GW | Pre-construction | pressurized water reactor | ||
| 5 | 1.25 GW | Pre-construction | pressurized water reactor | 2032 | |
| 6 | 1.25 GW | Pre-construction | pressurized water reactor | 2032 |
How nuclear power plants work
A nuclear power plant uses heat from controlled fission of uranium (or plutonium) fuel in a reactor core to produce steam, which drives a turbine-generator in the same way as a thermal power station. The reactor is surrounded by multiple safety barriers and a containment building.
Nuclear units typically run more than 90% of the hours in a year, so a single large reactor can supply several terawatt-hours of almost carbon-free electricity annually. Construction times are long and capital costs high, but fuel costs are low and plants are often licensed to operate for 60 years or more.
Technology at Khmelnitski nuclear power plant
Pressurised water reactors (PWR), the most common reactor type worldwide, keep the primary coolant under high pressure and transfer its heat to a separate steam circuit.
Location
Khmelnitski nuclear power plant is located in Khmelnytska, Ukraine, at approximately 50.3024, 26.6473. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Khmelnitski nuclear power plant is owned by SE NNEGC "Energoatom". Across the dataset, SE NNEGC "Energoatom" is linked to 5 power plants with 13.8 GW of operating capacity.
Frequently asked questions
What is the capacity of Khmelnitski nuclear power plant?
Khmelnitski nuclear power plant has a capacity of 2.00 GW according to the latest Global Energy Monitor data. This figure covers the 6 units or phases listed for the site.
What type of facility is Khmelnitski nuclear power plant?
Khmelnitski nuclear power plant is a nuclear power plant. Pressurised water reactors (PWR), the most common reactor type worldwide, keep the primary coolant under high pressure and transfer its heat to a separate steam circuit.
Who owns Khmelnitski nuclear power plant?
Khmelnitski nuclear power plant is owned by SE NNEGC "Energoatom".
Where is Khmelnitski nuclear power plant located?
It is located in Khmelnytska, Ukraine. Approximate coordinates: 50.3024, 26.6473.
Is Khmelnitski nuclear power plant operational?
According to the latest data, Khmelnitski nuclear power plant is in operation. Operating means the facility is built and in commercial service.
When did Khmelnitski nuclear power plant start operating?
Start year: 1988. Current status: Operating. Its 2 operating units were commissioned between 1988 and 2005. 2 further units or phases are scheduled to come online in 2032.
How much electricity does Khmelnitski nuclear power plant generate?
Actual output data are not published for every plant. As an indicative estimate, Khmelnitski nuclear power plant would produce about 15 TWh a year, assuming a capacity factor of 85%, which is typical for this technology.
How big is Khmelnitski nuclear power plant compared with other facilities in Ukraine?
Khmelnitski nuclear power plant ranks #4 by capacity among 4 comparable nuclear facilities tracked in Ukraine.