Overview
Global Energy Monitor tracks 4 units or phases at this site (operating 1.66 GW, planned 910 MW).
Technology: gas turbine, combined cycle; fuel: natural gas.
Ownership: SSE Thermal Ltd (parent company: SSE PLC).
Its 3 operating units were commissioned between 1996 and 2023. 1 further units or phases are scheduled to come online in 2027.
Why it matters
- The 4th-largest oil- and gas-fired power station in United Kingdom by capacity (of 98 operating oil & gas facilities tracked).
- Provides about 4.4% of United Kingdom's operating oil & gas capacity and roughly 1.7% of all operating power capacity in the country in the dataset.
- At a typical capacity factor of 40% for this technology, it would generate roughly 5.8 TWh of electricity a year (indicative estimate).
Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.
Oil & gas power in United Kingdom
United Kingdom has 37.7 GW of operating oil & gas capacity across 98 plants in the Global Energy Monitor dataset — 40% of the country's total operating power capacity of 95.1 GW.
The oil & gas pipeline in United Kingdom includes 2.12 GW under construction and 13.4 GW at earlier planning stages.
Other major oil & gas plants in United Kingdom include Drax power station (2.68 GW), Pembroke power station (2.31 GW) and Staythorpe C power station (1.77 GW).
See the full list: Gas & oil power plants in United Kingdom →
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| GT3 | 30 MW | gas turbine | 1996 | ||
| Unit 1 | 735 MW | combined cycle | 1996 | ||
| Unit 2, timepoint 1 | 893 MW | combined cycle | 2023 | ||
| Unit 3 | 910 MW | Pre-construction | combined cycle | 2027 |
How gas & oil power plants work
Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.
Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.
Technology at Keadby power station
Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant. Open-cycle gas turbines can start within minutes and are mainly used as peaking plants, at efficiencies of roughly 30–40%.
Location
Keadby power station is located in England, United Kingdom, at approximately 53.5944, -0.7504. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Keadby power station is owned by SSE Thermal Ltd. The ultimate parent company is SSE PLC. Across the dataset, SSE PLC is linked to 34 power plants in 3 countries, with 8.93 GW of operating capacity.
Frequently asked questions
What is the capacity of Keadby power station?
Keadby power station has a capacity of 1.66 GW according to the latest Global Energy Monitor data. This figure covers the 4 units or phases listed for the site.
What type of facility is Keadby power station?
Keadby power station is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Who owns Keadby power station?
Keadby power station is owned by SSE Thermal Ltd. The ultimate parent company is SSE PLC.
Where is Keadby power station located?
It is located in England, United Kingdom. Approximate coordinates: 53.5944, -0.7504.
Is Keadby power station operational?
According to the latest data, Keadby power station is in operation. Operating means the facility is built and in commercial service.
When did Keadby power station start operating?
Start year: 1996. Current status: Operating. Its 3 operating units were commissioned between 1996 and 2023. 1 further units or phases are scheduled to come online in 2027.
How much electricity does Keadby power station generate?
Actual output data are not published for every plant. As an indicative estimate, Keadby power station would produce about 5.8 TWh a year, assuming a capacity factor of 40%, which is typical for this technology.
How big is Keadby power station compared with other facilities in United Kingdom?
Keadby power station ranks #4 by capacity among 98 comparable oil & gas facilities tracked in United Kingdom.