Overview
Global Energy Monitor tracks 2 units or phases at this site (operating 1.47 GW).
Technology: combined cycle; fuel: natural gas.
Ownership: Electricity Generating PCL; Mit-Power (Thailand) Ltd; J-POWER Holdings (Thailand) Co Ltd (parent company: Electricity Generating PCL; Electric Power Development Co Ltd; Mitsui & Co Ltd).
Its 2 operating units were commissioned between 2007 and 2008.
Why it matters
- The 8th-largest oil- and gas-fired power station in Thailand by capacity (of 65 operating oil & gas facilities tracked).
- Provides about 4.3% of Thailand's operating oil & gas capacity and roughly 2.7% of all operating power capacity in the country in the dataset.
- At a typical capacity factor of 40% for this technology, it would generate roughly 5.1 TWh of electricity a year (indicative estimate).
Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.
Oil & gas power in Thailand
Thailand has 34.4 GW of operating oil & gas capacity across 65 plants in the Global Energy Monitor dataset — 64% of the country's total operating power capacity of 53.8 GW.
The oil & gas pipeline in Thailand includes 80 MW under construction and 10.5 GW at earlier planning stages.
Other major oil & gas plants in Thailand include Ratchaburi (RATCHGEN) power station (3.65 GW), Bang Pakong power station (3.27 GW) and Chonburi Ng Project power station (2.50 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| 1 | 734 MW | combined cycle | 2007 | ||
| 2 | 734 MW | combined cycle | 2008 |
How gas & oil power plants work
Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.
Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.
Technology at Kaeng Khoi 2 power station
Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Location
Kaeng Khoi 2 power station is located in Saraburi, Thailand, at approximately 14.6050, 101.0259. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Kaeng Khoi 2 power station is owned by Electricity Generating PCL; Mit-Power (Thailand) Ltd; J-POWER Holdings (Thailand) Co Ltd. The ultimate parent company is Electricity Generating PCL; Electric Power Development Co Ltd; Mitsui & Co Ltd. Across the dataset, Electricity Generating PCL is linked to 21 power plants in 7 countries, with 12.3 GW of operating capacity.
Frequently asked questions
What is the capacity of Kaeng Khoi 2 power station?
Kaeng Khoi 2 power station has a capacity of 1.47 GW according to the latest Global Energy Monitor data. This figure covers the 2 units or phases listed for the site.
What type of facility is Kaeng Khoi 2 power station?
Kaeng Khoi 2 power station is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Who owns Kaeng Khoi 2 power station?
Kaeng Khoi 2 power station is owned by Electricity Generating PCL; Mit-Power (Thailand) Ltd; J-POWER Holdings (Thailand) Co Ltd. The ultimate parent company is Electricity Generating PCL; Electric Power Development Co Ltd; Mitsui & Co Ltd.
Where is Kaeng Khoi 2 power station located?
It is located in Saraburi, Thailand. Approximate coordinates: 14.6050, 101.0259.
Is Kaeng Khoi 2 power station operational?
According to the latest data, Kaeng Khoi 2 power station is in operation. Operating means the facility is built and in commercial service.
When did Kaeng Khoi 2 power station start operating?
Start year: 2007. Current status: Operating. Its 2 operating units were commissioned between 2007 and 2008.
How much electricity does Kaeng Khoi 2 power station generate?
Actual output data are not published for every plant. As an indicative estimate, Kaeng Khoi 2 power station would produce about 5.1 TWh a year, assuming a capacity factor of 40%, which is typical for this technology.
How big is Kaeng Khoi 2 power station compared with other facilities in Thailand?
Kaeng Khoi 2 power station ranks #8 by capacity among 65 comparable oil & gas facilities tracked in Thailand.