Overview
Global Energy Monitor tracks 30 units or phases at this site (operating 1.02 GW, retired 1.89 GW).
Technology: gas turbine, subcritical; fuel: natural gas, fossil liquids: fuel oil, coal: bituminous.
Ownership: Tennessee Valley Authority.
Its 14 operating units were commissioned between 1975 and 2000. 16 units have already been retired (2015–2025). 10 operating units have a planned retirement date, the earliest in 2028.
Why it matters
- At a typical capacity factor of 50% for this technology, it would generate roughly 4.5 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in United States
United States has 167.4 GW of operating coal capacity across 181 plants in the Global Energy Monitor dataset — 13% of the country's total operating power capacity of 1,280.9 GW.
The coal pipeline in United States includes 6.24 GW under construction and 6.81 GW at earlier planning stages.
Other major coal plants in United States include Homer City Generating Station (4.71 GW), Parish Generating Station (3.95 GW) and Plant Bowen (3.50 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| G10 | 68 MW | gas turbine | 1975 | 2028 | |
| G11 | 68 MW | gas turbine | 1975 | 2028 | |
| G12 | 68 MW | gas turbine | 1975 | 2028 | |
| G13 | 68 MW | gas turbine | 1975 | 2028 | |
| G14 | 68 MW | gas turbine | 1975 | 2028 | |
| G15 | 68 MW | gas turbine | 1975 | 2028 | |
| G16 | 68 MW | gas turbine | 1975 | 2028 | |
| G17 | 85 MW | gas turbine | 2000 | ||
| G18 | 85 MW | gas turbine | 2000 | ||
| G19 | 85 MW | gas turbine | 2000 | ||
| G20 | 85 MW | gas turbine | 2000 | ||
| GT1 | 68 MW | gas turbine | 1975 | 2028 | |
| GT2 | 68 MW | gas turbine | 1975 | 2028 | |
| GT3 | 68 MW | gas turbine | 1975 | 2028 | |
| GT4 | 68 MW | Retired | gas turbine | 1975 | 2025 |
| GT5 | 68 MW | Retired | gas turbine | 1975 | 2025 |
| GT6 | 68 MW | Retired | gas turbine | 1975 | 2025 |
| GT7 | 68 MW | Retired | gas turbine | 1975 | 2025 |
| GT8 | 68 MW | Retired | gas turbine | 1975 | 2025 |
| GT9 | 68 MW | Retired | gas turbine | 1975 | 2025 |
| Unit 1 | 125 MW | Retired | subcritical | 1951 | 2017 |
| Unit 2 | 125 MW | Retired | subcritical | 1951 | 2017 |
| Unit 3 | 125 MW | Retired | subcritical | 1952 | 2017 |
| Unit 4 | 125 MW | Retired | subcritical | 1952 | 2017 |
| Unit 5 | 147 MW | Retired | subcritical | 1952 | 2015 |
| Unit 6 | 147 MW | Retired | subcritical | 1953 | 2015 |
| Unit 7 | 173 MW | Retired | subcritical | 1958 | 2015 |
| Unit 8 | 173 MW | Retired | subcritical | 1959 | 2015 |
| Unit 9 | 173 MW | Retired | subcritical | 1959 | 2015 |
| Unit 10 | 173 MW | Retired | subcritical | 1959 | 2015 |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Johnsonville Fossil Plant
Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity. Open-cycle gas turbines can start within minutes and are mainly used as peaking plants, at efficiencies of roughly 30–40%.
Location
Johnsonville Fossil Plant is located in Tennessee, United States, at approximately 36.0366, -87.9837. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Johnsonville Fossil Plant is owned by Tennessee Valley Authority. Across the dataset, Tennessee Valley Authority is linked to 54 power plants with 34.9 GW of operating capacity.
Frequently asked questions
What is the capacity of Johnsonville Fossil Plant?
Johnsonville Fossil Plant has a capacity of 1.02 GW according to the latest Global Energy Monitor data. This figure covers the 30 units or phases listed for the site.
What type of facility is Johnsonville Fossil Plant?
Johnsonville Fossil Plant is a coal-fired power station. Subcritical units are the oldest and least efficient coal-plant design, typically converting about 33–37% of the fuel's energy into electricity.
Who owns Johnsonville Fossil Plant?
Johnsonville Fossil Plant is owned by Tennessee Valley Authority.
Where is Johnsonville Fossil Plant located?
It is located in Tennessee, United States. Approximate coordinates: 36.0366, -87.9837.
Is Johnsonville Fossil Plant operational?
According to the latest data, Johnsonville Fossil Plant is in operation. Operating means the facility is built and in commercial service.
When did Johnsonville Fossil Plant start operating?
Start year: 1975. Current status: Operating. Its 14 operating units were commissioned between 1975 and 2000. 16 units have already been retired (2015–2025). 10 operating units have a planned retirement date, the earliest in 2028.
How much electricity does Johnsonville Fossil Plant generate?
Actual output data are not published for every plant. As an indicative estimate, Johnsonville Fossil Plant would produce about 4.5 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Johnsonville Fossil Plant compared with other facilities in United States?
Johnsonville Fossil Plant ranks #71 by capacity among 181 comparable coal facilities tracked in United States.