Overview
Global Energy Monitor tracks 2 units or phases at this site (under construction 1.00 GW).
Technology: combined cycle; fuel: natural gas.
Ownership: Guangdong Yuedian Huixin Thermal Power Co Ltd (parent company: Guangdong Electric Power Development Co Ltd; Huidong County Public Utility Development Group Co Ltd; Huizhou Industrial Investment Group Co Ltd).
2 further units or phases are scheduled to come online in 2027.
Why it matters
Gas-fired plants — especially combined-cycle units — provide flexible output that can ramp quickly to balance demand and variable renewables, so their availability is closely tied to gas supply and prices.
Oil & gas power in China
China has 193.9 GW of operating oil & gas capacity across 361 plants in the Global Energy Monitor dataset — 6.3% of the country's total operating power capacity of 3,086.2 GW.
The oil & gas pipeline in China includes 24.6 GW under construction and 64.9 GW at earlier planning stages.
Other major oil & gas plants in China include Sichuan Suining Anju Natural Gas power station (2.80 GW), Yudean Huizhou Gas power station (2.55 GW) and Dongguan Ningzhou Gas power station (2.48 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| 1 | 500 MW | Construction | combined cycle | 2027 | |
| 2 | 500 MW | Construction | combined cycle | 2027 |
How gas & oil power plants work
Gas- and oil-fired power plants burn fuel either in a gas turbine, a steam boiler or a reciprocating engine. In a combined-cycle plant the hot exhaust of the gas turbine is used to raise steam for a second, steam-driven turbine, lifting overall efficiency to 55–62%.
Because gas units can start quickly and change output within minutes, they play a central role in balancing electricity systems with growing shares of wind and solar. Their operating costs track fuel prices closely, so gas supply security — via pipelines or LNG — directly affects how often they run. A modern combined-cycle plant emits roughly 0.35–0.4 tonnes of CO₂ per megawatt-hour.
Technology at Guangdong Huizhou New Material Industrial Park power station
Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Location
Guangdong Huizhou New Material Industrial Park power station is located in Guangdong, China, at approximately 22.8946, 114.6054. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Guangdong Huizhou New Material Industrial Park power station is owned by Guangdong Yuedian Huixin Thermal Power Co Ltd. The ultimate parent company is Guangdong Electric Power Development Co Ltd; Huidong County Public Utility Development Group Co Ltd; Huizhou Industrial Investment Group Co Ltd. Across the dataset, Guangdong Electric Power Development Co Ltd is linked to 43 power plants with 47.4 GW of operating capacity.
Frequently asked questions
What is the capacity of Guangdong Huizhou New Material Industrial Park power station?
Guangdong Huizhou New Material Industrial Park power station has a capacity of 1.00 GW according to the latest Global Energy Monitor data. This figure covers the 2 units or phases listed for the site.
What type of facility is Guangdong Huizhou New Material Industrial Park power station?
Guangdong Huizhou New Material Industrial Park power station is a oil- and gas-fired power station. Combined-cycle units pair gas turbines with a heat-recovery steam generator and steam turbine, reaching efficiencies of 55–62% — the highest of any thermal power plant.
Who owns Guangdong Huizhou New Material Industrial Park power station?
Guangdong Huizhou New Material Industrial Park power station is owned by Guangdong Yuedian Huixin Thermal Power Co Ltd. The ultimate parent company is Guangdong Electric Power Development Co Ltd; Huidong County Public Utility Development Group Co Ltd; Huizhou Industrial Investment Group Co Ltd.
Where is Guangdong Huizhou New Material Industrial Park power station located?
It is located in Guangdong, China. Approximate coordinates: 22.8946, 114.6054.
Is Guangdong Huizhou New Material Industrial Park power station operational?
According to the latest data, Guangdong Huizhou New Material Industrial Park power station is under construction. Under construction means physical work has started on site but the facility is not yet in commercial service.
When is Guangdong Huizhou New Material Industrial Park power station expected to start?
Start year: 2027. Current status: Construction. 2 further units or phases are scheduled to come online in 2027.
How big is Guangdong Huizhou New Material Industrial Park power station compared with other facilities in China?
Guangdong Huizhou New Material Industrial Park power station ranks #85 by capacity among 448 comparable oil & gas facilities tracked in China.
Nearby energy infrastructure
- Yudean Huizhou Gas power station
- Shenzhen Energy Fengda Gas Thermal power station
- Huizhou Cogen power station
- Huizhou Daya Bay Petrochemical Zone Comprehensive Energy Station
- Huadian Huizhou Dongjiang Gas cogeneration power station
- Ling'ao nuclear power plant
- Daya Bay nuclear power plant
- Huizhou LNG Terminal