Overview
Global Energy Monitor tracks 4 units or phases at this site (operating 2.00 GW, under construction 2.00 GW).
Technology: ultra-supercritical; fuel: coal: unknown.
Ownership: Jiangxi Datang International Fuzhou Power Generation Co Ltd (parent company: Datang International Power Generation Co Ltd; Electricité de France SA).
Its 2 operating units were commissioned between 2015 and 2016. 2 further units or phases are scheduled to come online in 2027.
Why it matters
- At a typical capacity factor of 50% for this technology, it would generate roughly 8.8 TWh of electricity a year (indicative estimate).
Coal-fired units are typically run as baseload or mid-merit plants and are the most carbon-intensive form of power generation, which makes their retirement schedules a key indicator of national transition plans.
Coal power in China
China has 1,259.6 GW of operating coal capacity across 1,188 plants in the Global Energy Monitor dataset — 41% of the country's total operating power capacity of 3,086.2 GW.
The coal pipeline in China includes 93.1 GW under construction and 145.8 GW at earlier planning stages.
Other major coal plants in China include Beilun power station (7.10 GW), Pingwei power station (6.54 GW) and Togtoh power station (6.12 GW).
Units and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Phase I Unit 1 | 1.00 GW | ultra-supercritical | 2015 | ||
| Phase I Unit 2 | 1.00 GW | ultra-supercritical | 2016 | ||
| Phase II Unit 3 | 1.00 GW | Construction | ultra-supercritical | 2027 | |
| Phase II Unit 4 | 1.00 GW | Construction | ultra-supercritical | 2027 |
How coal power plants work
A coal-fired power station burns pulverised coal in a boiler to turn water into high-pressure steam, which spins a turbine connected to a generator. After passing through the turbine the steam is condensed back into water — usually with river, sea or cooling-tower water — and pumped back to the boiler.
Efficiency depends mainly on steam temperature and pressure: older subcritical units convert roughly a third of the coal's energy into electricity, while modern supercritical and ultra-supercritical units reach 40–47%. Each megawatt-hour from coal emits roughly 0.8–1.1 tonnes of CO₂, the highest of any major power source, which is why many countries have set coal phase-out dates.
Technology at Fuzhou power station
Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.
Location
Fuzhou power station is located in Jiangxi, China, at approximately 27.7845, 116.5644. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Fuzhou power station is owned by Jiangxi Datang International Fuzhou Power Generation Co Ltd. The ultimate parent company is Datang International Power Generation Co Ltd; Electricité de France SA. Across the dataset, Datang International Power Generation Co Ltd is linked to 132 power plants with 72.4 GW of operating capacity.
Frequently asked questions
What is the capacity of Fuzhou power station?
Fuzhou power station has a capacity of 2.00 GW according to the latest Global Energy Monitor data. This figure covers the 4 units or phases listed for the site.
What type of facility is Fuzhou power station?
Fuzhou power station is a coal-fired power station. Ultra-supercritical units operate at the highest steam temperatures and pressures used in coal plants, reaching efficiencies of around 43–47%.
Who owns Fuzhou power station?
Fuzhou power station is owned by Jiangxi Datang International Fuzhou Power Generation Co Ltd. The ultimate parent company is Datang International Power Generation Co Ltd; Electricité de France SA.
Where is Fuzhou power station located?
It is located in Jiangxi, China. Approximate coordinates: 27.7845, 116.5644.
Is Fuzhou power station operational?
According to the latest data, Fuzhou power station is in operation. Operating means the facility is built and in commercial service.
When did Fuzhou power station start operating?
Start year: 2015. Current status: Operating. Its 2 operating units were commissioned between 2015 and 2016. 2 further units or phases are scheduled to come online in 2027.
How much electricity does Fuzhou power station generate?
Actual output data are not published for every plant. As an indicative estimate, Fuzhou power station would produce about 8.8 TWh a year, assuming a capacity factor of 50%, which is typical for this technology.
How big is Fuzhou power station compared with other facilities in China?
Fuzhou power station ranks #155 by capacity among 1188 comparable coal facilities tracked in China.