Hydropower · Russia

Bureyskaya hydroelectric plant

Bureyskaya hydroelectric plant is a 2.01 GW hydropower plant located in Amur Oblast, Russia. The facility is currently in operation, with its first unit entering service in 2003.

2.01 GWCapacity
OperatingStatus
2003Start year
View on the interactive map →

Overview

Technology: conventional storage.

Ownership: PJSC RusHydro.

Why it matters

  • The 8th-largest hydropower plant in Russia by capacity (of 85 operating hydropower facilities tracked).
  • Provides about 3.8% of Russia's operating hydropower capacity and roughly 0.8% of all operating power capacity in the country in the dataset.
  • Ranks #79 worldwide among hydropower facilities of the same status group by capacity.
  • At a typical capacity factor of 40% for this technology, it would generate roughly 7.0 TWh of electricity a year (indicative estimate).

Hydropower provides renewable electricity and, where reservoirs exist, dispatchable output and storage that help stabilise the grid; output varies with rainfall and river flows.

Hydropower power in Russia

Russia has 52.4 GW of operating hydropower capacity across 85 plants in the Global Energy Monitor dataset — 22% of the country's total operating power capacity of 240.2 GW.

The hydropower pipeline in Russia includes 840 MW under construction and 4.19 GW at earlier planning stages.

Other major hydropower plants in Russia include Sayano-Shushenskaya hydroelectric plant (6.40 GW), Krasnoyarsk hydroelectric plant (6.00 GW) and Bratsk hydroelectric plant (4.50 GW).

See the full list: Hydropower plants in Russia →

How hydropower plants work

Hydropower plants convert the energy of falling or flowing water into electricity: water passes through turbines placed at the foot of a dam or along a diversion channel, and the turbines drive generators. Output depends on the height of the water drop (the head) and the volume of water flowing.

Reservoir and pumped-storage schemes can store energy and release it within minutes, which makes hydropower one of the most flexible sources on the grid. Annual generation varies with rainfall and snowmelt, and large dams can have significant effects on river ecosystems and downstream water use.

Technology at Bureyskaya hydroelectric plant

Its reservoir allows water to be stored and power to be dispatched when it is most needed.

Location

Imagery © Esri, Maxar, Earthstar Geographics

Bureyskaya hydroelectric plant is located in Amur Oblast, Russia, at approximately 50.2701, 130.3136. Open the interactive map to explore nearby power plants, high-voltage lines and substations.

Ownership

Bureyskaya hydroelectric plant is owned by PJSC RusHydro. Across the dataset, PJSC RusHydro is linked to 38 power plants with 28.0 GW of operating capacity.

Frequently asked questions

What is the capacity of Bureyskaya hydroelectric plant?

Bureyskaya hydroelectric plant has a capacity of 2.01 GW according to the latest Global Energy Monitor data.

What type of facility is Bureyskaya hydroelectric plant?

Bureyskaya hydroelectric plant is a hydropower plant. Its reservoir allows water to be stored and power to be dispatched when it is most needed.

Who owns Bureyskaya hydroelectric plant?

Bureyskaya hydroelectric plant is owned by PJSC RusHydro.

Where is Bureyskaya hydroelectric plant located?

It is located in Amur Oblast, Russia. Approximate coordinates: 50.2701, 130.3136.

Is Bureyskaya hydroelectric plant operational?

According to the latest data, Bureyskaya hydroelectric plant is in operation. Operating means the facility is built and in commercial service.

When did Bureyskaya hydroelectric plant start operating?

Start year: 2003. Current status: Operating.

How much electricity does Bureyskaya hydroelectric plant generate?

Actual output data are not published for every plant. As an indicative estimate, Bureyskaya hydroelectric plant would produce about 7.0 TWh a year, assuming a capacity factor of 40%, which is typical for this technology.

How big is Bureyskaya hydroelectric plant compared with other facilities in Russia?

Bureyskaya hydroelectric plant ranks #8 by capacity among 85 comparable hydropower facilities tracked in Russia.

Other assets of the same owner

Sources and methodology

Source: Global Energy Monitor, Global Integrated Power Tracker, 2026-09 release. Full project profile on GEM.wiki. Last updated: 8 October 2026.

Capacity, status, ownership and unit details come from Global Energy Monitor's public trackers, which are compiled from company reports, government filings and news coverage and updated several times a year. Rankings and shares are calculated by The Daily Energy from the same dataset. Estimated annual generation uses typical capacity factors for each technology and is indicative only.

Data: Global Energy Monitor (GIPT 2026-09, GGIT 2025-11, GOIT 2026-06, GOGET 2026-03, GCMT 2026-08, OSM 2026-10) licensed under CC BY 4.0; transmission grid © OpenStreetMap contributors (ODbL). Compiled and published by The Daily Energy.

Special projects