Overview
The tracker lists 12 trains, units or expansion phases at the terminal.
Capacity is expressed in million tonnes per annum (mtpa) of LNG that can be received and regasified.
One mtpa of LNG corresponds to roughly 1.36 billion cubic metres of natural gas per year, so this capacity equals about 3.9 bcm/y of gas.
Ownership: Southern LNG Company LLC (parent company: Blackstone Inc; Kinder Morgan Inc; unknown).
Its 10 operating units were commissioned between 2019 and 2020. 1 units have already been retired.
Why it matters
- The 3rd-largest LNG import (regasification) terminal in United States by capacity (of 5 operating lng import terminal facilities tracked).
Import terminals regasify liquefied natural gas delivered by tanker and inject it into the grid, giving countries access to seaborne gas supply from many exporters.
LNG terminals in United States
The dataset tracks 39 lng terminals in United States, including operating, planned and shelved projects.
United States has 45.9 mtpa of operating LNG import capacity across 5 terminals.
United States has 258.0 mtpa of operating LNG export capacity across 8 terminals.
Trains and phases
| Unit / phase | Capacity | Status | Technology | Start | Retired |
|---|---|---|---|---|---|
| Import Terminal | 12.0 mtpa | Retired | 1978 | ||
| Optimization Project | 0.40 mtpa | Proposed | |||
| T05 | 0.25 mtpa | 2019 | |||
| T01 | 0.25 mtpa | 2019 | |||
| T04 | 0.25 mtpa | 2019 | |||
| T02 | 0.25 mtpa | 2019 | |||
| T06 | 0.25 mtpa | 2020 | |||
| T07 | 0.25 mtpa | 2020 | |||
| T08 | 0.25 mtpa | 2020 | |||
| T09 | 0.25 mtpa | 2020 | |||
| T10 | 0.25 mtpa | 2020 | |||
| T03 | 0.25 mtpa | 2019 |
How lng terminals work
An LNG import terminal receives liquefied natural gas from tankers, stores it at around −162 °C in insulated tanks and warms it back into gas (regasification) before sending it into the pipeline grid. Many newer terminals are floating storage and regasification units (FSRUs), which can be installed much faster than onshore plants.
Import terminals give countries access to gas from many exporters worldwide, improving supply security and price competition — a role that became especially visible in Europe after 2022.
Location
Elba Island LNG Terminal is located in Georgia, United States, at approximately 32.0911, -81.0003. Open the interactive map to explore nearby power plants, high-voltage lines and substations.
Ownership
Elba Island LNG Terminal is owned by Southern LNG Company LLC. The ultimate parent company is Blackstone Inc; Kinder Morgan Inc; unknown. Across the dataset, Blackstone Inc is linked to 2 lng terminals.
Frequently asked questions
What is the capacity of Elba Island LNG Terminal?
Elba Island LNG Terminal has a capacity of 2.90 mtpa according to the latest Global Energy Monitor data. This figure covers the 12 units or phases listed for the site.
What type of facility is Elba Island LNG Terminal?
Elba Island LNG Terminal is a LNG import (regasification) terminal.
Who owns Elba Island LNG Terminal?
Elba Island LNG Terminal is owned by Southern LNG Company LLC. The ultimate parent company is Blackstone Inc; Kinder Morgan Inc; unknown.
Where is Elba Island LNG Terminal located?
It is located in Georgia, United States. Approximate coordinates: 32.0911, -81.0003.
Is Elba Island LNG Terminal operational?
According to the latest data, Elba Island LNG Terminal is in operation. Operating means the facility is built and in commercial service.
When did Elba Island LNG Terminal start operating?
Start year: 1978. Current status: Operating. Its 10 operating units were commissioned between 2019 and 2020. 1 units have already been retired.
How big is Elba Island LNG Terminal compared with other facilities in United States?
Elba Island LNG Terminal ranks #3 by capacity among 5 comparable lng import terminal facilities tracked in United States.